INSTALLATION
CONSIDERATIONS FOR INSTALLATION
Note1: A+B = CU (Stroke used) CD = (Available stroke) = 300/400/500 mm
Opening
angle
A
B
Cu
90
80
80
160
90
90
180
100
100
200
100
150
250
100
110
110
220
120
120
240
120
100
220
110
130
130
260
140
140
280
150
150
300
Opening
angle
A
B
Cu
90°
Available
stroke =
400mm
160
160
320
175
175
350
190
190
380
200
200
400
90°
Available
stroke =
500mm
250
250
500
TABLE 1
·
The installation and testing operations must be performed solely by qualified personnel in order
to guarantee the proper and safe operation of the automatic gate.
·
The company declines any responsibility for damage caused by incorrect installations due to
incompetence and/or negligence.
·
Before assembling the automatism, check that the gate is in perfect working order, hangs well
on its hinges and is suitably lubricated. It must also comply with the safety standards in force
in the country of installation..
1. Before fastening the brackets provided, establish the coordinates using the data given in
Table 1,
bearing in mind that they are valid if the operator is at maximum extension minus one
centimetre of the available stroke
(CD)
when the gate is closed to obtain maximum working
efficiency.
2. Data
B
in the table, with reference to the single values
A
, are to be considered as values
(recommended).
3. To anchor the piston, use the fastening brackets provided.
COORDINATES AND TABLE
1. Establish coordinates
A + B
that are
to be used.
2.
Note:
The stroke used
(CU)
of the
operator must never be equal or
greater than the available stroke (
CD)
3. The sum of coordinates
A + B,
establishes the stroke used
CU .