Preparation of the electrical connection
The section Installation is directed towards the electrical specialist.
WARNING
Improper installation.
Personal and material damage.
Configure the fuse in front of the energy storage system as three-pole.
The fuse must meet the requirements of a separator
Secure the device connection on the energy store with a 16 A fuse type B.
Comply with the switch-off conditions pursuant to VDE 0100-410.
Never connect the energy storage system without a PE and N connection.
There must be a suitable separator (e.g. a selective circuit breaker) be-
tween the mains and the customer’s system with which the customer’s
system can be separated from the mains on an all-pole basis in the event
of maintenance works.
Adhere to the indicated line cross-sections.
Note:
For the position of the separators, see the connection drawings in the appendix.
Use your personal protective equipment.
This reduces the risk of injuries during the mechanical works.
Adhere to the safety rules.
Disconnect from the mains.
Secure against switching on again.
Ensure de-energised state.
Before connecting to energy, ensure that there are no persons in the danger zone.
Содержание pulse neo
Страница 1: ...VARTA STORAGE GMBH OPERATING MANUAL VARTA pulse neo ...
Страница 16: ...16 System overview Identification Type plate and ID label Cryptocode label ID label of the battery module ...
Страница 35: ...35 All dimensions in millimetres Fig 2 Dimensions on the support plate ...
Страница 77: ...As at 07 2021 Appendix a Connection diagram TN C network ...
Страница 78: ...As at 07 2021 Appendix b Connection diagram TT network ...
Страница 79: ...As at 07 2021 Appendix c Connection diagram TN C network with data logger ...
Страница 80: ...As at 07 2021 Appendix d Connection diagram TT network with data logger ...