0020257297_06 Installation and maintenance instructions
65
▶
Start with the second test.
Result 3:
The pressure increases and there is residual moisture:
▶
Carry out the drying process.
▶
Start with the second test.
9.
Second test
: Switch on the vacuum pump.
10.
Drain the refrigerant pipes and the indoor unit's plate
heat exchanger.
–
Absolute pressure to be reached: 0.1 kPa
(1.0 mbar)
–
Running time of the vacuum pump: 30 minutes
11.
Switch off the vacuum pump.
–
Waiting period: 3 minutes
12.
Check the pressure.
Result 1:
Pressure is stable:
▶
The second test is complete. Close the ball valves
(2)
and
(4)
.
Result 2:
The pressure increases.
▶
Repeat the second test.
5.11
Adding additional refrigerant
Danger!
Risk of injury due to escaping refrigerant.
Touching any escaping refrigerant may
cause injury.
▶
Wear personal protective equipment.
1.
Determine the basic length of the refrigerant pipe.
2.
Calculate the required volume of additional refrigerant.
Product
Basic length
Refrigerant volume
VWL 35/5 and
VWL 55/5
< 15 m
None
15 m to 25 m
30 g for every addi-
tional metre (above
15 m)
25 m to 40 m
300 g + 47 g for
every additional
metre (above 25 m)
Product
Basic length
Refrigerant volume
VWL 75/5
< 15 m
None
15 m to 25 m
70 g for every addi-
tional metre (above
15 m)
25 m to 40 m
700 g + 107 g for
every additional
metre (above 25 m)
Product
Basic length
Refrigerant volume
VWL 105/5 and
VWL 125/5
< 15 m
None
15 m to 25 m
70 g for every addi-
tional metre (above
15 m)
25 m to 40 m
700 g + 83 g for
every additional
metre (above 25 m)
Condition
: Length of the refrigerant pipe > 15 m
▶
Ensure that the two isolation valves on the outdoor unit
are still closed.
R410A
2
3
4
5
1
▶
Connect the refrigerant fitting
(2)
with the ball valve
(1)
to
a refrigerant cylinder
(4)
.
–
Refrigerant to be used: R410A
▶
Put the refrigerant cylinder on the scales
(5)
. If the refri-
gerant cylinder does not have an immersion sleeve, put it
on the scales upside down.
▶
Leave the ball valve
(3)
closed. Open the refrigerant cyl-
inder and the ball valve
(1)
.
▶
If the hoses have been filled with refrigerant, set the
scales to zero.
▶
Open the ball valve
(3)
. Fill the outdoor unit with the cal-
culated refrigerant volume.
▶
Close both of the ball valves.
▶
Close the refrigerant cylinder.
5.12
Releasing the refrigerant
Danger!
Risk of injury due to escaping refrigerant.
Touching any escaping refrigerant may
cause injury.
▶
Wear personal protective equipment.
1
1.
Remove both covering caps
(1)
.
2.
Unscrew both hexagon socket screws as far as they
will go.
◁
The refrigerant flows into the refrigerant pipes and
the indoor unit.
Содержание VWL 105/5 AS S2
Страница 203: ......