71
Commissioning
Check that the gas supply pressure,
gas rate and heat input are in
accordance with the Technical Data
in Table 1 of these instructions.
IMPORTANT:
•
When commissioning a new
installation for the first time, ensure
that all air has been purged from
the storage tank and installation
pipework before attempting to light
the boiler. If difficulty is experienced
in lighting the boiler for the first
time during commissioning,
particularly with a bulk storage tank
installation, it is very likely that
there is still air present in the gas
supply. Contact your gas supply
company to check that the
installation has been purged
correctly.
•
Please ensure that the enclosed
sticker is affixed to the storage tank
(or bottle store) in a clearly visible
position, preferably close to the
filling point.
•
Please ensure that the storage tank
is only filled with propane
according to BS 4250; point I.
Specification for commercial Butane
and Propane.