commissioning
vacon • 99
24-hour support: +358-(0)40-
8371 150 • Email: vacon@vacon.com
8
9
Run the start-up tests without the motor being connected to the process. If this is not
possible, make sure that running each test is safe prior to running it. Inform your co-
workers of the tests.
a)
Switch off the DC supply voltage and wait until the drive has stopped as advised in
Chapter 8.1, step 5.
b)
Connect the motor cable to the motor and to the motor cable terminals of the inverter.
c)
Make sure that all Start/Stop switches are in Stop positions.
d)
Switch the supply voltage ON
e)
Repeat test 8A or 8B.
10
Connect the motor to the process (if the start-up test was run without the motor being
connected)
a)
Before running the tests, make sure that this can be done safely.
b)
Inform your co-workers of the tests.
c)
Repeat test 8A or
8B.
Содержание NXI
Страница 1: ...vacon nxi inverters fi9 fi14 user manual ...
Страница 24: ...24 vacon installation Tel 358 201 2121 Fax 358 201 212 205 5 Figure 5 2 Vacon NXI dimensions FI10 ...
Страница 26: ...26 vacon installation Tel 358 201 2121 Fax 358 201 212 205 5 Figure 5 4 Vacon NXI dimensions FI12 front view ...
Страница 104: ......