8
vacon • 94
Options
Local contacts: http://drives.danfoss.com/danfoss-drives/local-contacts/
8.6.1
Installation
Figure 63. Cover open (MU2 3-phase example).
1
•
Remove the HMI cap and the cover from the drive. See the Figure 63.
2
•
Open only the inlet holes where you need to run the cables. Cables pass
through this inlet hole.
3
•
Connect the supply cable to the Mains switch passing through the cable gland
from the bottom side (use the cable gland for sealing the cable to the drive)
and then through the terminal box as shown in the figure below.
4
•
Place the Mains switch with the cables inside the drive and fix it with its
screws.
5
•
Connect the cables from the Mains switch to the line terminal. The cables have
to be connected to the terminals L1, L2 and L3.
NOTE:
•
For single-phase version connect BLU cable to N and BROWN cable to L.
6
•
Fix the cables with cable clamp.