Installation, Operation and Maintenance Manual
C13-Series
21
Subject to change without notice.
10.20-IM (0818)
Thermostat
Standard units (no heating) with one compressor require
single stage thermostats, cool only� Units with two require
dual stage thermostats, cool only�
When a programmable thermostat is used, a sixth contact
must be added to the terminal board in the evaporator
section� Three connections must be made from this sixth
contact…
(1)
to the programmable thermostat,
(2)
to a
ground and
(3)
to the 24 volt coil of the evaporator fan motor
contactor (K2)� See Figure 15�
Heat pump units and units with auxiliary electric heat (either
integral in unit or in duct) require single stage, cool/heat
heat pump thermostats if units have only one compressor�
Units with two compressors require dual stage heat pump
thermostats with cool/ heat functions�
Figure 13: Adding Sixth Contact
Checking Hot Gas Bypass Valve
1�
Connect a calibrated thermocouple lead to the outlet
line at the hot gas bypass valve� Tie wrap and insulate
the lead�
2�
Connect a low pressure refrigerant gauge to the suction
line�
3�
Connect a high pressure refrigerant gauge to the liquid
line�
4�
Operate air conditioner in the cooling mode until
system is stabilized� (Approximately 15 minutes)
5�
If the high side pressure is not at or above 400 psig,
block off the condenser inlet air stream until the
pressure is above this threshold� This will simulate a
system performance level close to the design condition
of 95° F ambient�
6�
The hot gas bypass valve setting is 104 psig�
a�
If the suction pressure is 104 psig the thermocouple
reading should be approximately 117° F or higher�
Please note that it may be necessary to block off
some of the evaporator air in order to check this
condition�
b�
If the suction pressure is above 104 psig the
thermocouple reading should be less than 117° F�
c�
If the suction pressure is below 104 psig the hot
gas bypass valve should be adjusted to raise the
pressure�
Cut tubing at an angle so that bottom
of reservoir doesn’t close it� Be sure
tubing does not interfere with float.
Figure 11: Condensate Tubing Termination
Figure 12: Condensate Pump and Trap Installation
18' Max�
To
Drain
Inverted "U" Trap
Programmable Thermostat
Evaporator
Section
Enclosure
Terminal
Board
R
G
Y
1
Y
2
T
C
K2
Evaporator Fan
24 Volt Coil
New Sixth
Contact to be Added
Ground
1
2
3
Содержание C13-Series
Страница 2: ......