Put the stillwell assembly into the enclosure. It stands on the enclosure
floor at the back. Clamp the stillwell to the bracket with the stainless
steel hose clamp supplied.

5.3.1

Connect The Stillwell To The Pan

A flexible hose is used to link the stillwell to the evaporation pan. It is
normally buried to protect it from accidental damage. This hose ensures that
the water level in the pan and stillwell are the same at all times.

An air lock could form in the hose if there are any high points. This can
restrict or block water transfer and prevent the system from operating
correctly.

To keep the hose straight, sleeve it with a piece of 40mm PVC pipe before it
is buried. This also serves as a duct for the fill hose and the drain pump cable.
Lay the sleeved hose into a shallow trench between the stillwell and pan. Cut
the hose to length and connect it to the pan, using a hose clamp.

Automatic Evaporation System

INSTALLING THE EQUIPMENT 21

Stillwell

6541-31/C (can be
rotated 90° on
stillwell)

m12.5 hose to
evaporation pan

Stillwell mounting
bracket and battery
shelf

Enclosure

SS hose clamp

5.3.2

Fill The Pan And Set The Water Level Instrument

Fill the pan with water to near the reference point in the pan level gauge.
Check the hose connections and the pan for leaks and fix any problems.

Confirm that the water level in the stillwell is the same as in the evaporation
pan, and that they move together. An airlock in the hose system can prevent
this happening. To check, take some water from the pan and almost fill the
stillwell. Check that it drains back to the previous level. If it doesn’t, clear the
air lock.

To clear an airlock, remove the hose from the level gauge and blow through it
until it bubbles into the stillwell. Replace the hose and confirm the water
transfer is OK.

5.3.3

Prepare The Float System And Stillwell Assembly

Do the following:

1.

Bolt the Model 6541-31/C instrument to the stillwell cap, with the two
bolts provided. The instrument must be fitted with a
100mm-circumference float pulley and an offset pulley.

2.

Prepare the float system. This is normally supplied as an assembly, ready
for installation. However, if you need to prepare it yourself, follow these
steps:

- Loop one end of the floatline through the eye of the float. Use two
crimps to fix the loop.

- Place the float in the bottom of the stillwell. Thread the floatline up
through the centre hole in the stillwell cap. Place the cap and instrument
in position on the stillwell.

UNIDATA

22 INSTALLING THE EQUIPMENT

Содержание STARLOG 6529

Страница 1: ...may be reproduced transmitted transcribed stored in a retrieval system or translated into any language or computer language in any form or by any means electronic mechanical magnetic optical chemical...

Страница 2: ...he Water Level Instrument 23 5 3 5 Set And Test The System 24 5 4 The Level Control System 25 5 4 1 Overview 25 5 4 2 Level Control Module 26 Automatic Evaporation System i 5 4 3 Fill System 26 5 4 4...

Страница 3: ...een pan evaporation and site conditions This is required for evaporation and evapo transpiration studies and modelling An optional telemetry system can be connected to the datalogger Landline cellular...

Страница 4: ...E or later and are supplied on disk with initial releases of the instrument Alternatively you can obtain this update from the technical support section on the UNIDATA web site www unidata com au Refer...

Страница 5: ...ngs Intake Bulkhead fitting for 12 5mm ID hose Connects level gauge to stillwell Refill Bulkhead fitting for 12 5mm ID hose Connects level control system to pan Pan weight 12kg Mounting Timber frame 1...

Страница 6: ...el on top of cabinet Model 6529A 3 Float system inside PVC 115mm float line counterweight and offset guide pulley Hose 12 6mm heavy duty flexible hose 1 8 metres long Two stainless steel hose clamps s...

Страница 7: ...rain Pump Type Marine bilge pump Located in pan Cable length 2 metres Power 12 volts 1 2 amps Capacity Maximum 20 litres minute Housing PVC enclosure attached to inside of pan Drain Hose 12 5mm hose c...

Страница 8: ...rable with a manual pan Automatic Evaporation System EVAPORATION MONITORING TECHNIQUES 11 3 1 Using Evaporation Pan Data The daily total evaporation can vary from 0 on a cool and misty day to more tha...

Страница 9: ...sites and data quality is compromised Water level too high will result in rainfall splashing or blowing from the tank when it is near full and overflowing when it is full Water level below the referen...

Страница 10: ...tomatic Evaporation System SITE REQUIREMENTS AND LAYOUT 15 4 1 1 Water Supply The evaporation pan is refilled each day by the level control system The automated refill is controlled by a solenoid swit...

Страница 11: ...y tank on stand Optional hose from drain pump Enters top of tank to prevent siphoning 1 metre head Model 6529 2L Low Pressure Solenoid 0 70kPa mounted in enclosure 4 1 4 Underground Supply Where the w...

Страница 12: ...in the middle of the evaporation pan 5 2 Installing The Model 6529A Enclosure The stillwell enclosure is located 1 5 metres from the pan on the side away from the equator where it will not shadow the...

Страница 13: ...ment Fill the pan with water to near the reference point in the pan level gauge Check the hose connections and the pan for leaks and fix any problems Confirm that the water level in the stillwell is t...

Страница 14: ...stalled on both the float pulley and offset pulley check that the float and counterweight can rise freely from the bottom to the top of the stillwell without clashing or touching the sides 6 Rotate th...

Страница 15: ...ar powered battery system A regulator on the switch card manages battery charging All devices connect to the row of pluggable terminals located at the front of the enclosure Automatic Evaporation Syst...

Страница 16: ...lifted from the well separated in the middle and the pump lifted out for cleaning The bottom of the pump can be removed to clean and service the impeller The pump must be inverted when installed for r...

Страница 17: ...t hole of the three at the bottom of the left hand wall of the cabinet Attach the hose to the pan and seal it with a hose clamp Connect the pan end of the hose to the fitting in the top hole of the pa...

Страница 18: ...mm water level falls and the rainfall data all 0 2mm rises The data is logged in increments of 0 4mm The effects of any pan water level resets and minor water level pulsations are not recorded The tim...

Страница 19: ...following settings are recommended for a normal project You may prefer a 15 minute log interval to reduce the volume of logged data Click on the Events panel to open the listing of events Double clic...

Страница 20: ...elect Scheme from the toolbar then Save As Automatic Evaporation System OPERATING THE SITE 35 The Log Buffer Panel The Events Detail Panel You should save it with a scheme name that identifies your si...

Страница 21: ...NG THE SITE 37 6 5 Data Recovery And Review Refer to the software manual for Version 3 Software for detailed descriptions on operating the software and displaying data Select Display a Data File from...

Страница 22: ...ration and rainfall data is the accumulated total since the logger was last reset It may contain corrupting events if there has been any artificial water level changes There are two shown in the above...

Страница 23: ...ed spare parts and check instruments Take the visit file Automatic Evaporation System SITE VISITS AND MAINTENANCE 41 7 1 2 Carrying Out The Site Inspection At the site your objectives are to Recover t...

Страница 24: ...ariations Automatic Evaporation System SITE VISITS AND MAINTENANCE 43 6 Check that the derived rainfall is sensible and supported by the evaporation data 7 Select the ASCII report The file will be sav...

Страница 25: ...hould be added to the station visit file to remind the site operator to attend to the matter at the next site visit The interaction between site operation data processing reporting and review allows f...

Страница 26: ...7 3 5 Solenoid Pump Regularly check the operation of the solenoid and pump To check the condition and serviceability of the solenoid and or pump 1 Connect each device to the TEST position of the cont...