TYROLIT
Hydrostress AG
Page 17
Ring saw HRE400
Preparatory operations
The work is prepared as follows:
1.
Determine conditions:
–
Location of supply lines in walls, floors and ceilings
–
Cooling water drainage (risk of electric shock and water damage)
2.
Secure the site.
3.
Secure cut-outs in walls, ceilings and floors (e.g. crane or supports). Take weight of concrete
into consideration (1 m
3
corresponds to 2400-2700 kg). Determine position and sequence of
cuts.
4.
Perform a visual inspection of the ring saw.
Position and order of cuts
Define position
X
Obtain information about the concrete or masonry to be sawn:
–
Where does the reinforcement run?
–
Is it heavily or slightly reinforced?
X
Cut across the concrete if possible
Define the sequence of cuts
Using the wrong cut sequence can result in the disk grinding ring getting jammed.
X
Define cutting sequence (for example, for a window cutout carry out the bottom cut first,
then the side cuts and finally the top cut).
4
4.1
4.1.1
4.1.2