Appendix B Installation and Commissioning Checklists
Node Start-up and Commissioning Checklist
Release TR3.2.1
Turin Networks
Page 12-35
Node Start-up
and
Commissioning
Checklist
Basic precautions and procedures for handling cards and electrostatic discharge
protection are provided in Section 6—
Precautions and Common Procedures
Chapter 1—“Precautions,” page 6-1 and Chapter 3—“Inserting and Removing Cards,”
page 6-15.
All Traverse node start-up and commissioning detail-level procedure references are to
Section 11—
Node Start-up and Commissioning Procedures
. Required equipment and
tools are also provided as part of start-up and card placement chapters.
Important:
Always wear a properly grounded ESD wrist strap when
handling and placing cards into the Traverse shelf. Plug the ESD wrist
strap into the ESD jack provided on the air ramp or other confirmed source
of earth ground.
OPTIC WARNING!
Follow all directions and warning labels when
working with optical fibers. Always wear eye protection when working
with optical fibers. Never look directly into the end of a terminated or
unterminated fiber or connector as it may cause eye damage.
Table 12-12 Node Start-up and Commissioning Checklist
Step
Description and Procedure Reference
D
1
Switch on Power to the Traverse Shelves (nodes).
Battery “A” and “B” PDAP-2S circuit breakers, PDAP-4S TPA
fuse holders, and PDAP-15A GMT fuse holders are located on the
front of the PDAP. Switch the PDAP-2S circuit breakers to the
ON position or install an operable PDAP-4S TPA or PDAP-15A
GMT fuse for each installed shelf beginning with A1 and B1.
Leave the other PDAP-2S circuit breakers in the OFF position or
PDAP-4S TPA or PDAP-15A GMT fuse holders empty.
Important:
The input power and critical alarm LEDs display on
the PDAP indicating no cards are place in the Traverse shelf. The
fan tray holder power LED is green.
Refer to Chapter 1—“Node Start-up and Commissioning,”
2
Insert the Active GCM in Slot GCMA or GCMB.
Important:
The GCM power LED is solid green indicating that
the GCM has power. The solid green Active/Standby LEd
indicates that it is the active GCM card. Initial configuration is
done through the active GCM via the CLI.
Содержание TransNav
Страница 5: ...Release TR3 2 1 Turin Networks Page iii Installation and Commissioning Checklists 12 21 Index Index 1 ...
Страница 6: ...Page iv Turin Networks Release TR3 2 1 ...
Страница 14: ...Traverse Installation and Commissioning Guide Calling for Repairs Page xii Turin Networks Release TR3 2 1 ...
Страница 101: ...Chapter 1 Power Interface Specifications PDAP 4S Release TR3 2 1 Turin Networks Page 4 3 ...
Страница 316: ...Traverse Installation and Commissioning Guide Section 12 Appendices Page ii Turin Networks Release TR3 2 1 ...
Страница 361: ......
Страница 362: ...Visit our website at www turinnetworks com Release TR3 2 1 Traverse System Documentation 800 0002 TR321 ...