Commissioning
Before you start commissioning:
Check active chilled beams for correct position
Remove protective films, if any
Ensure that all connections are correct
Ensure that all active chilled beams are clean
and free from residues and foreign matter
Ensure that the water system including the
heat exchanger has been filled and vented
Commissioning
Carry out the following steps for commissioning:
Switch on the ventilation system.
Switch on the supply voltage (for devices with
volume flow controller).
Check the cooling and/or heating operating
modes (open/close valves).
Set the airflow direction on the grille.
Cleaning
Cleaning the casing
The casing may be cleaned with a damp cloth.
Sticky dirt or contamination may be removed with a
commercial, non-aggressive cleaning agent.
Cleaning agents that contain chlorine must not be
used.
Cleaning the heat exchanger
Personnel:
Specialist personnel
Protective equipment:
Industrial safety helmet
Safety shoes
Protective gloves
CAUTION!
Hot surface!
Danger of burn or scald injuries when working on
the hot water system.
Before working on the unit, shut down the
system, depressurise it and let it cool down.
CAUTION!
Danger of cutting your fingers on the fins of
the heat exchanger
The heat exchanger has thin fins, which are very
sharp; when you touch them, there is a danger of
your cutting your fingers.
To avoid injuries, proceed carefully and wear pro-
tective gloves when you work on the heat
exchanger.
1.
To clean the heat exchanger, depending on
the installation situation, disassemble the
secondary air grille or open the cleaning
opening.
2.
Carefully clean the heat exchanger with an
industrial vacuum cleaner. Be careful to not
damage the fins. We recommend using a
soft brush with the suction inlet.
3.
After cleaning, screw-fix the grille and close
the cleaning opening.
Commissioning
Active chilled beams Type DID-E2
13
Содержание DID-E2 Series
Страница 15: ...Active chilled beams Type DID E2 15...
Страница 16: ...Active chilled beams Type DID E2 16...