17 

Revision D March 2021

 

Trinity Highway Approved Adhesive Anchoring System 

A  Trinity  Highway  approved  adhesive  anchoring  system  is  required  to  securely  anchor  crash 
cushions. Each approved adhesive kit contains adhesive, studs, nuts and washers. Both vertical 
and horizontal assemblies are possible using an approved adhesive anchoring system. 

Vertical Anchors 

Note:  

Read all Trinity Highway approved adhesive instructions before starting.

 

1)  Prepare the Concrete Foundation

 

Warning:

  Do not allow anchoring adhesive to contact skin or eyes. See material 

safety data sheet supplied with adhesive kit for first-aid procedures. Use only in 
well-ventilated area. Do not use near open flame. 

Warning:

    It  is  the  responsibility  of  the  installer  to  maintain  a  safe  work  area 

including the use of standard work zone safety equipment & PPE:  gloves, safety-
toe shoes, and eye / ear protection. 

The  anchor  bolts  (studs)  that  anchor  the  QuadGuard

®

  M  Wide  Backup  and/or  Monorail 

sections to the concrete foundation must be those shipped in the kit or of high strength steel 
(120,000  psi  [830  MPa]  minimum  tensile  strength  or  equal).  These  studs  must  be  set  in 
minimum 4000 psi [28 MPa] concrete. Allow the concrete to cure a minimum of seven days 
before applying anchoring adhesive. 

2)  Drill Boreholes 

Caution:

   

It  is  the  responsibility  of  the  installer  to  consult  OSHA  silica 

respiratory standard 29 CFR 1910.134 for debris removal from borehole(s) 
and  use  Trinity  Highway  approved  adhesive  to  achieve  optimum  tensile 
strength. Do not use diamond drill bits for drilling boreholes. 

Use the Monorail(s) and Tension Strut Backup as drilling templates. Use a rotary hammer drill 
to drill the boreholes 

7/8” [22 mm]

 diameter to the recommended depth. See the approved 

adhesive instructions provided with adhesive kit. Check ensure each borehole is drilled to the 
proper depth and aligned with the part to be anchored per Anchoring Information table.

 

Anchoring Information

 

Stud Size: 

Orientation 

Bit Size 

Minimum Depth 

Torque 

Medium 

3/4”X7" 

Vertical 

7/8” [22 mm]

 

5 3/4” [145 mm] 

Adhesive 

Manufacturer Spec

 

Concrete 

3)  Clean the Boreholes 

Blow the concrete dust from the borehole using oil-free compressed air. Thoroughly brush it 
with a 7/8” diameter steel bristle tube brush and then blow it out again. If the borehole is wet, 
completely flush it with water while brushing and then blow it clean to remove all water using 
oil-free compressed air. 

Note:

 

 Use of the Trinity Highway approved vacuum drilling equipment is authorized to replace 

the blowing and brushing requirement of Step 3. 

Содержание QuadGuard M Wide

Страница 1: ......

Страница 2: ...maintenance and repair of the QuadGuard M Wide could result in serious injury or death Important These instructions are for standard assembly specified by the appropriate highway authority In the eve...

Страница 3: ...ency 37 Visual Drive By Inspection 37 Walk Up Inspection Checklist 37 Post Impact Instructions 38 Parts Ordering Procedure 40 Drawings 42 QuadGuard M Wide Tension Strut Backup QFMTSCVR U 42 Concrete P...

Страница 4: ...ssembled in the location specified by the appropriate highway authority If there are deviations alterations or departures from the assembly protocol specified in this manual the device may not perform...

Страница 5: ...M Wide Additional copies of this manual are available from Trinity Highway by calling 888 323 6374 or by visiting TrinityHighway com Product Please contact Trinity Highway if you have any questions c...

Страница 6: ...way or by third parties The QuadGuard M Wide is intended to be assembled delineated and maintained within specific state and federal guidelines It is important for the highway authority specifying the...

Страница 7: ...ickup trucks at speeds of up to 62 mph 100 kph at redirection angles up to 25 degrees During head on impact testing within MASH criteria the QuadGuard M Wide has been shown to telescope rearward to ab...

Страница 8: ...M Bill of Materials and system drawings shipped with your system Please call Trinity Highway if you have any system questions p 3 Note Components are not shown to scale Tension Strut Backup 69 Diaphra...

Страница 9: ...G 611368 611375 611379 Hinge Plate Fender Panel Hinge Plate Full Length Hinge Pin Dia Full Length 610172 627524 627525 Tel ST 1 3 4X1 3 4X12 GAX10 Tel ST 2X2X12 GAX10 Pipe 3 4 Schedule 80X2 5 16 61575...

Страница 10: ...et Cart Support Nose Washer Bar 10GAX2X14 626815 626816 626818 Nose L QG M Wide Nose R QG M Wide 627513 627514 Bolt Hex 1 4X3 4 G5 Bolt Hex 1 4X1 G5 Bolt Hex 3 8X1 G5 113518 113508 113596 Bolt Hex 3 8...

Страница 11: ...8 1 2 G8 113666 119163 116879 Bolt Hex 3 4X2 G8 Rail Bolt 5 8X2 Stud 3 4X7 G5 113555 003400 117542 Nut Hex 1 4 Nut Hex 3 8 Rail Nut Hex 5 8 115946 115960 003340 Nut Hex 5 8 Nut Heavy Hex 3 4 Washer Lo...

Страница 12: ...arch 2021 Washer Fender 3 8X2 Washer Flat 5 8X1 3 4 Washer Flat 3 4X2 Hvy 118038 003300 118027 Die Spring 1 1 2 ODX3 4X6 Mushroom Washer Approved Adhesive 117458 617045 118710 Cartridge Assy Type I Ca...

Страница 13: ...c and what type of barrier or road feature the QuadGuard M Wide is shielding Contact Customer Service prior to deployment if you have any questions p 3 Important The QuadGuard M Wide is available with...

Страница 14: ...ves Safety toe Shoes Protective Clothing Reflective Vest Cutting equipment Rotary Hammer Drill Rebar cutting bit Concrete drill bits 7 8 22 mm Double Fluted Grinder Hacksaw or Torch optional Important...

Страница 15: ...ns provided in this manual have been strictly followed Miscellaneous Traffic control equipment Lifting and moving equipment A lifting device is preferred although a forklift can be used Minimum 5 000...

Страница 16: ...aller to ensure proper site grading for the QuadGuard M Wide placement as dictated by the state or specifying agency pursuant to the AASHTO Roadside Design Guide Caution Accurate placement of all stee...

Страница 17: ...s otherwise determined by the resident project engineer or appropriate highway authority Recommended dimension and reinforcement specifications for new concrete pads can be found on the standard drawi...

Страница 18: ...crete Allow the concrete to cure a minimum of seven days before applying anchoring adhesive 2 Drill Boreholes Caution It is the responsibility of the installer to consult OSHA silica respiratory stand...

Страница 19: ...upplied with the approved adhesive kit 7 Torque the Nuts Once the adhesive has fully cured torque the nut to the adhesive manufacturer s recommended values Anchor Assembly Cautions 1 Steel rebar If st...

Страница 20: ...tud so the nut is flush with end of stud 3 Insert each Stud with Washer and Nut into Borehole Push stud with washer and nut into borehole Important The stud should be flush with the top of the nut in...

Страница 21: ...evision D March 2021 Figure 12 Elevation View 6 Bay TL 3 6 5 4 1 2 3 Figure 11 Plan View TYPE II CARTRIDGES FRONT BACK KEY 1 Backup 2 Quad Beam Fender Panel 3 Nose 4 Cartridge 5 Diaphragm 6 Monorail 3...

Страница 22: ...in the Nose of each system Note There will always be one more Cartridge in the system than the number of Bays in the system To determine number of Bays count Fender Panels on one side Figure 13 Measur...

Страница 23: ...nterline of the system Mark a construction line parallel to the center line and offset 6 5 165 mm to one side as shown in Figure 15 The edge of the Monorail will be positioned on this line Note The co...

Страница 24: ...before anchoring Backup Caution Every hole in the Backup and Monorail must be anchored by a stud using an approved adhesive 3 Anchor the Monorail Monorail Placement for Tension Strut Backup Figure 17...

Страница 25: ...After Applied Torque ANCHOR WASHER ROADWAY BACKUP OR MONORAIL NUT CAUTION 1 1 2 38 mm Maximum Anchor height Top surfaces must be flush Tongues must be fully inserted and flush Detail A Figure 18 Rail...

Страница 26: ...and hex nut two 2 places per brace and four 4 places per side D Secure each diagonal brace set in two 2 places with a 3 8 hex bolt lock washer and hex nut Figure 20 Note A Side Panel is unnecessary wh...

Страница 27: ...Figure 22 The widest Diaphragm must be attached closest to the Backup with each subsequent Diaphragm being progressively narrower Important Slide the widest Diaphragm all the way to the Backup to ensu...

Страница 28: ...gm Figure 25 See pages 46 and 47 for additional information 8 Attach Fender Panels Important Do not mix the 5 8 rail nuts large with the 5 8 hex nuts small Figure 26 Important For proper impact perfor...

Страница 29: ...Panel Step 2 Slide the Fender Panel forward until the holes in the Fender Panel line up with the holes in the forward Diaphragm Hinge Plate Step 3 Use a drift pin to align the center hole of the Fende...

Страница 30: ...tighten the Mushroom Washer Assembly small hex nut until it reaches the end of the screw threads Assemble the remaining Diaphragms and Fender Panels following the same procedure Tighten rail nuts larg...

Страница 31: ...2021 9 Attach End Cap Attach the End Cap to the front of the first Monorail segment as shown below and the Monorail Assembly drawing Figure 30 Monorail End Cap Attachment MONORAIL 5 8 LOCK WASHER 5 8...

Страница 32: ...Diaphragms and also to the front of the Backup as shown below Figure 32 Cartridge Support Bracket Assembly Tension Strut Backup TENSION STRUT BACKUP Figure 31 Lower Cartridge Support Bracket Assembly...

Страница 33: ...8X2 hex bolts and rail nuts Tighten Detail D E D Attach Nose to Fender Panel and Diaphragm Hinge Plates with 5 8 rail nuts Adjust Nose assembly height so top front Nose is 32 1 8 above the concrete p...

Страница 34: ...4 HEX NUT Detail D Steel Nose not shown for clarity 5 8 RAIL NUT PULLOUT BRACKET Detail E Inside View Nose Cover Cut Away Detail F Inside view back of front diaphragm showing nuts against Hinge Plate...

Страница 35: ...Bracket Assembly 3 8 HEX NUT 3 8X1 HEX BOLT 3 8 FLAT WASHER 3 8X2 FLAT WASHER CARTRIDGE HOLD DOWN BRACKET 3 8 HEX NUT ANGLE BRACKET 3 8 WASHER Detail G Note height of the Nose Cartridge Support Brack...

Страница 36: ...el Gap Wide 1 00 25 mm Figure 35 Fender Panel Gap 12 Cartridge Placement The Nose Cartridge must be the same height as every other Cartridge To complete the assembly of a QuadGuard M Wide place the ap...

Страница 37: ...p 20 Every hole and slot in Backup and Monorail is anchored pp 23 24 If no transition side panels at backup are required p 25 Anchor stud s are 1 5 maximum above the pad p 24 Monorail guides are attac...

Страница 38: ...inspection Walk Up Inspection Checklist Clear and dispose of on site debris Clear and remove excessive dirt from around the Monorail and Diaphragm feet Bolts are tight and rust free Anchor bolts are...

Страница 39: ...t so the system can be restored to its original position Caution Use eye protection and gloves when refurbishing the Mushroom Washer Die Spring Assembly Do not place fingers underneath an assembled Mu...

Страница 40: ...for these overlapping parts including Fender Panels overlapping Panels behind the system is 1 00 25 mm Important Ensure the Mushroom Washer rail nuts are tightened to the end of the bolt threads If th...

Страница 41: ...to Vertical Concrete End Shoe None Parts List s Quantities PN Description Count 118710 Adhesive HY200 330 Hilti 14 627511 Backup TS 64 M Wide W Decals 1 113518 Bolt Hex 1 4x3 4 G5 6 113508 Bolt Hex 1...

Страница 42: ...Screw Flat 5 8X8 1 2 G8 Socket 12 614062 Shim 12GAX3 5 8X8 12 117458 Spring Die 1 1 2 ODX3 4X6 12 117542 Stud 3 4X7 G5 56 615756 Tel ST 1 3 4X1 3 4X12GAX10 H4S 4 615765 Tel ST 2X2X12GAX10 H4S 4 626818...

Страница 43: ...TrinityHighway com 42 Revision D March 2021 QuadGuard M Wide Tension Strut Backup QFMTSCVR U Drawings...

Страница 44: ...TrinityHighway com 43 Revision D March 2021 Concrete Pad 618686...

Страница 45: ...TrinityHighway com 44 Revision D March 2021 TS Concrete Pad 8 w Rebar 618686...

Страница 46: ...TrinityHighway com 45 Revision D March 2021 TS Concrete Pad 8 wo Rebar 618686...

Страница 47: ...TrinityHighway com 46 Revision D March 2021 Tension Strut Backup 627528...

Страница 48: ...TrinityHighway com 47 Revision D March 2021 Monorail Assembly 625637...

Страница 49: ...TrinityHighway com 48 Revision D March 2021 Diaphragm Assembly 627534...

Страница 50: ...TrinityHighway com 49 Revision D March 2021...

Страница 51: ...TrinityHighway com 50 Revision D March 2021...

Страница 52: ...TrinityHighway com 51 Revision D March 2021 Shim Kit 627518...

Страница 53: ...TrinityHighway com 52 Revision D March 2021 Fender Panel Assembly 608241...

Страница 54: ...TrinityHighway com 53 Revision D March 2021 Nose Assembly 627522...

Страница 55: ...TrinityHighway com 54 Revision D March 2021 End Shoe Transition 627729...

Страница 56: ...TrinityHighway com 55 Revision D March 2021 31 W Beam Guardrail Transition QFMTSCVR TWLR...

Страница 57: ...TrinityHighway com 56 Revision D March 2021 Thrie Beam Transition QFMTSCVR TTLR...

Страница 58: ...TrinityHighway com 57 Revision D March 2021 Safety Shape Barrier Transition QFMTSCVR T4LRF...

Страница 59: ...TrinityHighway com 58 Revision D March 2021 Single Slope Transition QFMTSCVR T6LRF...

Страница 60: ...TrinityHighway com 59 Revision D March 2021 QuadGuard M Wide TS w Block QFMTSCVR UVB...

Страница 61: ...TrinityHighway com 60 Revision D March 2021 Vertical Barrier Transition QFMTSCVR ESLR...

Страница 62: ...TrinityHighway com 61 Revision D March 2021 TS Concrete Pad w Block 627903...

Страница 63: ...TrinityHighway com 62 Revision D March 2021...

Страница 64: ......

Отзывы: