5.8. Manually testing emergency units
After all emergency units have been installed, addressed and identified, the function and duration time of the units
must be tested.
During the test, the emergency units to be tested are switched on. A status line in the x/e-touchPANEL indicates the
type of test (FT ›function test‹, DT ›duration test‹, CT ›communication test‹) and the respective groups. The status
line is located at the bottom right of the touchpanel while the test is running.
The batteries have been charged for at least 24 hours.
Click on the "Main menu" symbol.
-> The "Main menu" is displayed
Click on the "Commissioning Test" button.
-> The dialog box "Start test" is displayed.
Select the check box "start function test" or "start duration test" and confirm with OK.
-> The selected test is performed and displayed in the status line.
After the test has been completed, click on the Test protocol symbol:
-> The Test protocol window is displayed.
I
NOTICE
Depending on the emergency unit, the duration test can take up to three hours.
The batteries must be charged for a minimum of 24 hours before the duration test can be started.