Start-Up Procedures
c
Check Vent Piping and Combustion Air
Piping.
Check for gas-tight seal at every con-
nection and seam of the venting and
combustion air piping.
Venting system must be sealed gas-tight
to prevent flue gas spillage and potential
carbon monoxide emissions, which will
result in severe personal injury or death.
c
Check Gas Piping
Check around the unit for gas odor fol-
lowing the procedure outlined in this
manual on Page 39.
If any gas leaks are found or suspected,
shut the unit down immediately. Use a
gas detection device or bubble test to
locate the source of the gas leak and
repair at once. Do not operate the unit
until the leak is corrected. Failure to
comply with this procedure could result
in severe personal injury, death or sub-
stantial property damage.
c
Verify Flame Pattern and Combustion
Check the flame pattern through the
inspection port of the heat exchanger.
The flame should be blue and stable.
The flame should be the length of the
burner head openings.
The combustion testing and adjustments
must be performed by a qualified
installer, service agency or the gas suppli-
er. All combustion measurements must be
performed with calibrated equipment to
ensure proper reading and accuracy.
Test for CO2 or O2 and for CO during
high firing rate. To manually place the
boiler into high fire mode, reference
page 45. The combustion reading
should be within the range listed in
Table 2.
The CO level should not
exceed 100 ppm when combustion is
correct.
The combustion levels should be mea-
sured at high firing rate, refer to page 45
of the PRESTIGE Solo control section
on how to set the firing rate. If the com-
bustion levels are not within the range
given in Table 2 for the firing rate, shut
the boiler down and contact Triangle
Tube Engineering Department. Failure
to comply with this requirement could
result in severe personal injury, death or
substantial property damage.
c
Measure Input - Natural Gas Only
1. Ensure the boiler is firing at maximum firing
rate. To manually place the boiler into high
fire mode, reference page 45.
2. Operate the unit for approximately 10
minutes.
3. Turn off all gas appliances within the build-
ing, except the PRESTIGE Solo.
4. At the gas meter, record the time required
to use one cubic foot of gas.
WARNING
WARNING
WARNING
WARNING
Table 2: Recommended Combustion Levels
Содержание Prestige Slol 250
Страница 61: ...55 Factory Setting Parameters FACTORY SETTING FOR PARAMETERS ...
Страница 72: ...65 Replacement Parts 5 9 8 1 3 5 2 6 7 Fig 26 PRESTIGE Solo Jacket Components ...
Страница 73: ...66 Replacement Parts 8 5 9 2 3 4 4 6 7 1 Fig 27 PRESTIGE Solo 60 Internal Components ...
Страница 74: ...67 Replacement Parts 8 5 4 4 10 9 7 1 3 2 6 Fig 27A PRESTIGE Solo 175 250 Internal Components ...
Страница 75: ...68 Replacement Parts 8 7 10 1 2 3 4 4 5 6 9 Fig 27B PRESTIGE Solo 399 Internal Components ...
Страница 77: ...70 Replacement Parts 7 6 9 1 2 10 12 13 4 3 5 8 Fig 28A PRESTIGE Solo 399 Burner Components ...
Страница 78: ...71 3 Fig 29 PRESTIGE Solo Electronic Components Replacement Parts ...
Страница 80: ...73 Product Specifications Front View PRESTIGE Solo 175 250 ...
Страница 83: ...76 Product Specifications Side View PRESTIGE Solo 175 250 ...