Coil & Piping Installation Checks
Coils water In/OUT piping connected correctly.
Condensate drain and P-trap been installed correctly / primed
External pipe fittings complete and pipes properly supported
Coil Headers of specified material
Valves installed in correct direction
Filter Instalation Checks
Are the air filters installed with proper orientation?
Filter Diffrential Pressure Switch operation?
Mixing Box / Economizer Dampers
Outdoor Air Damper Operation check
Return Air Damper Operation check
Exhaust Air Damper Operation check
Have the air dampers been inspected?
Supply Duct Installation Checks
3D requirement
Duct visibly sound, clean, sealed & in good condition
Ducts have no apprarent flow restriction.
Ducts have turning vanes in square elbows
Notes:
Put a check or an “X” in the box if the indicated item is “OK”
Put “NA” in the box if the item does not apply.
Put “BO” in the box if the work is was performed by Others
(include appropriate explanation)
Pre-Start Up Checklist
Содержание TRANE Quantum CLCPEuro
Страница 2: ...TRANE R...
Страница 6: ...TRANE R 2 CLCPXP Model Nomenclature...
Страница 7: ...TRANE R CLCPEURO Model Nomenclature 3...
Страница 13: ...TRANE R Assembly Installation CLCPEuro CLCPXP External connection 9...
Страница 14: ...TRANE R Assembly Installation CLCPEuro Break Point 25mm Frame to Frame 10...
Страница 15: ...TRANE R 11 Assembly Installation CLCPEuro Break Point 25mm Panel to Frame...
Страница 16: ...TRANE R 12 Assembly Installation CLCPEuro Break Point 2 50mm Frame to Frame...
Страница 17: ...TRANE R Assembly Installation CLCPEuro Break Point 2 50mm Panel to Frame 13...
Страница 18: ...TRANE R Assembly Installation CLCPEuro Paneling 14...
Страница 19: ...TRANE R Assembly Installation CLCP XP Break Point 15...
Страница 20: ...TRANE R Assembly Installation CLCP XP Break Point 16...
Страница 21: ...TRANE R 17 Assembly Installation CLCP...
Страница 22: ...TRANE R Assembly Installation CLCP 18...
Страница 36: ...TRANE R Maintenance 32 Figure 18 Belt Tension Measurement...
Страница 39: ...TRANE R 35 Trouble Analysis Pulley and Belt...
Страница 45: ...TRANE R Appendix B HDT Unit Weight CLCPXP 41...
Страница 46: ...TRANE R Appendix B HDT Unit Weight CLCPXP 42...
Страница 47: ...TRANE R Appendix B HDT Unit Weight CLCPXP 43...
Страница 48: ...TRANE R Appendix B VDT Unit Weight CLCPXP 44...
Страница 52: ...TRANE R Appendix D Filter and Quantity 48 Filter Dimension and Arrangement High Capacity Filter CLCP Euro only...
Страница 53: ...TRANE R Appendix D Filter and Quantity 49 Filter Dimension and Arrangement Final Filter HEPA...
Страница 57: ...TRANE R Typical Wiring Diagram Starter Star Delta 380 420V 3Phase 4Wires ELCB Standard 53...
Страница 58: ...TRANE R 54 Typical Wiring Diagram Starter Dol 380 420V 3Phase 4Wires ELCB Standard...
Страница 59: ...TRANE R 55 Typical Wiring Diagram Starter Dol 380 420V 3Phase 4Wires Standard...
Страница 60: ...TRANE R 56 Typical Wiring Diagram VFD Starter Dol Bypass Starter C W Door Switch 380 415 440 460V 3Phase 3Wires...
Страница 61: ...TRANE R 57 Typical Wiring Diagram Starter Dol 380 420V 3Phase 4Wires ELCB Enhance with Thermistor Relay...
Страница 62: ...TRANE R 58 Typical Wiring Diagram Starter Dol 380 420V 3Phase 4Wires Standard...
Страница 63: ...TRANE R 59 Typical Wiring Diagram Starter Dol 380 420V 3Phase 4Wires Enhance with Thermistor Relay...
Страница 64: ...TRANE R 60 Typical Wiring Diagram Starter Star Delta 380 420V 3Phase 4Wires Enhance with Thermistor Relay...
Страница 65: ...TRANE R 61 Typical Wiring Diagram Starter Star Delta 380 420V 3Phase 4Wires Standard...
Страница 68: ...TRANE R 64...
Страница 70: ...TRANE R 66...
Страница 71: ...TRANE R...