CenTraVac Commissioning Checklist
Job Name
Location
Model #
Serial #
Sales Order #
Start-up Date
Note: The Unit Installation, Operation and Maintenance Manuals including Warning and Cautions, Applicable Service
Alerts and Bulletins, Submittals, and Design Specifications must be used in conjunction with this checklist.
I.
PRE-COMMISSIONING PROCEDURES
A. Obtain Pre-commissioning Check Sheet
This must be prepared by installer for a particular unit, verifying the unit is ready for commissioning.
B.
Obtain Design (order) Specification Data
This indicates the design criteria of the particular unit. A unit cannot be properly commissioned unless this data is
known. It is the responsibility of the selling office to furnish this data.
C.
Obtain Wiring Diagrams
The “as-wired” electrical diagram should be compatible with the recommended Trane submittals and diagrams. Are
customer added external/remote control circuits compatible?
Yes
No
D.
General Installation Observations
1. Is there any apparent shipping or rigging damage?
Yes
No
2. Record the unit pressure upon receipt: psig. If there is no pressure, a leak test will have to be done be-
fore the unit can be evacuated and charged.
3. Is the water piping correctly installed?
Flow Switches
Yes
No
Pressure Gauges
Yes
No
Isolations Valves
Yes
No
Flow Balancing Valves
Yes
No
Thermometer Wells
Yes
No
Vent Cocks and Drains
Yes
No
4. Have proper clearances around the unit been maintained per submittal and/or Installation? Are there Manual
guidelines available
Yes
No
5. Is power wiring of adequate ampacity and correct voltage?
Yes
No
6. Is the unit base acceptable, level, and is the unit on isolators (rubber as supplied by Trane or spring type)?
Yes
No
7. Have the low voltage circuits been properly isolated from the higher voltage control and power circuits?
Yes
No
E.
Comments
78