STEP • 10
STEP • 11
06
10b.
This is the last remaining panel. So, this panel will need
screwing down on both sides (As Shown). Once competed,
check that the shed is square and screw to the base.
4ft WINDOW PANEL
4ft WINDOW PANEL
Attach The Next 4ft
Window Panel
= Drill Points using
screws provided as shown
x2
4.0 x 70mm
Per Floor Section
x3
x6
4.0 x 70mm
10a.
This is the last remaining panel. So, fix
this panel to the other sections using 6 screws
total (3 screws per side).
= Drill Points using
screws provided as shown
6ft APEX ROOF GABLE ENDS
APEX ROOF GABLE ENDS
(Set Frame for roof sections)
Now attach all the 6ft Apex
Gable Ends and the 6ft Apex
Truss
11a.
Place the the roof Gable Ends as shown
below. The 2 outer sections will be fully
framed as below and any centre trusses will
fit in between all panel meeting points.
11b.
Truss must sit in between panel sections
where two panels meet.
Ensure the Gable Ends slot neatly in to the current
Tongue & Groove over lower section, then screw
down using the framework behind.
6ft GABLE END
6ft TRUSS
x2
4.0 x 70mm
Per Floor Section
x3
x2
4.0 x 70mm
Per TOP Panel
© Sheds (Midlands) Limited 2021