5
5.1 Check Before Operation
Before switching power on and starting the product, check the switch settings, installation
and wiring again that they conform to the instructions given in this Operation Manual and
the Manual for Monitoring and Control Network Installation and Wiring (6F8C0880).
If any error is found, correct it according to these manuals.
(1) Checking the switch settings: Check the switch settings using the Engineering tool.
(Host ID setting switches, operation mode setting switches)
(2) Installation check: Check the installation, referring to the Manual for Monitoring and
Control Network Installation and Wiring.
(3) Wiring check: Check the wiring, referring to the Manual for Monitoring and Control
Network Installation and Wiring.
5.2 Starting
The system starts operating automatically when power is switched on.
When the EN6 modules start, check that they are operating normally, referring to Table
2-1 (page 10) in Chapter 2.
If the modules fail to start, or if their operation is not normal, stop use and contact the
nearest Toshiba service office.
5.3 Stopping
The system stops when power is switched off.