NOTE
If your cleanroom requires seismic anchoring, be sure to adhere to local seismic codes.
For example:
Prior to installing wall panels, drill and install an anchor every 4’ along the base frame about 2” from the vertical frame, and one
into the base of the door frame underneath the control panel. The holes should be drilled into the base frame approximately 2”
away from the vertical frame posts. Avoid drilling through the corner inserts or through the connector pieces; drill only through
the H-frames. For the top face of the base frame, drill a 5/8” hole to fit the anchor. Directly beneath it, drill a ½” hole. The concrete
should be a minimum of 6” deep and field verified. Use 3/8” Kwik Bolt TZ (not included) for a minimum embedment of 3-5/8”.
The diagram below is an example, local seismic codes may vary.