3. Installing the Ceiling Components: FFUs, Light, Duplex Cable, and Ceiling Panels
To prevent damage to the delicate filter medium, always exercise care when handling
Fan Filter Units!
Handle FFUs by the frame only; do NOT apply pressure to the filter face.
CAUTION
A.
Verify that each FFU speed control is set at “Medium.”
Install the FFUs by carefully lowering each into the
appropriate opening in the ceiling support frame (see following page for location). Each module should fit snugly
against the ceiling grid frame to form a tight seal. No fasteners are necessary to hold these modules in place.
B.
Install the light modules by carefully lowering each into the appropriate opening in the ceiling support frame. The
light fixture should fit snugly against the ceiling grid frame to form a tight seal. No fasteners are necessary to hold
it in place.
C.
Control Panel Switchbox is installed to the right of the access door. The power cable extends from the switch
box, through the vertical upright and out at the top of the ceiling joist. Verify that this cable is attached to the
connector labeled “To Switch Connection” on the Power Distribution Module.
D.
The duplex power outlet is installed inside the buffer room. To complete the electrical connection, run the power
cable that extends above the duplex receptacle to the Power Distribution Module, and complete the connections
as shown below and on the following page.
Figure 3: Ceiling Fixtures –
Including
lights, FFUs, and Power distribution
module.