ADCP-96-088 • Issue 2 • 6/2013
Page 6
© 2013, Tyco Electronics Corporation. All Rights Reserved.
2.3
Cabinet Installation Hardware
The cabinet is shipped with various parts (see
) that are used for securing the cabinet to
the FMS or PMF. Verify that the parts specified are received.
2.4
OSP Cable and Cabinet Grounding Cables
The cabinet is equipped with a common grounding block that is used to tie together all the
components of the cabinet that must be grounded. The cabinet itself and any OSP cables with
metallic strength members must be connected to an earth ground source. Information on
grounding is provided in the sections that cover cabinet mounting.
2.5
Tools and Materials Required for Installation
The following tools and materials are required for cabinet installation:
All Cabinet Installations
• Hammer
• Wire cutter
• Utility knife
• Screwdriver (flat blade)
• 9/16-inch wrench
• Torque wrench (with 7/16-inch socket and standard screwdriver socket)
• Tape measure
• Pen or marker
• 216B key tool (accessory - required to open cabinet door)
• 3/16-inch hex-key (required to open riser security panel)
• 7/32-inch hex-key (required to remove lifting eyes)
• Padlock (optional)
• Grounding system, copper wire, and grounding clamp (per local requirements)
• Splicing equipment for splicing OSP feeder and distribution cables
• Lifting equipment for hoisting the cabinet into position for mounting
• Level
• Excavation and earth moving equipment
• Landscaping equipment and site restoration supplies
Table 2. Cabinet Installation Hardware
ITEM
QUANTITY
3/8 x 1-inch hex head capscrews
8
3/8-inch flat washers
8
3/8-inch lock washers
8
Isolation gasket
1