FLANGING MACHINE
17
F-400
5.1.3 LEVELING
The machine should be installed on a solid and level foundation, preferably on a concrete
bed.
- Required floor load capacity 3.0 t/m²
- Floor level ± 5 mm /m²
The F-400 machine must be leveled on its foundation before use. The leveling tolerance is
0,05mm on 1000mm. Use a spirit level.
After leveling, fastening the machine to the foundation by means of anchor bolts is
recommended. Use anchor bolts M12 x 150… 200 mm.
Screw M12, Washer Ø 13, Hole in anchor foot Ø 17, Anchor bolt M12
Remove the protective grease from the machine using a detergent, which will not
damage plastic or rubber parts.