Side 1 and 2: Cut the connection profiles to the
correct length and mount them on the correct sides
(see Fig. 44)
•
Side 3 and 4: Cut the connection profiles to the
correct length and mount them on the correct sides
(see Fig. 37).
Fig. 46 - Unit of unequal width - situation C
•
Side 1: Cut the connection profile to the correct
length and mount it on the correct side (see Fig.
36).
•
Side 2: Cut the connection profile to the correct
length and mount it on the correct side (see Fig.
44).
•
Side 3: Cut the connection profile to the correct
length and mount it on the correct side (see Fig.
37).
•
Side 4: Cut the connection profile to the correct
length and mount it on the correct side as
described below.
Fig. 47 - Roof finish, situation C, side 4
•
Mount Z-profiles over the projecting cross beam
of the top section as described below. The plastic
roof foil of the bottom casing section can be
applied over these profiles.
Fig. 48 - Roof finish, projecting cross beam
Fig. 49 - Unit of unequal width - situation D
•
Side 1 and 2: Cut the connection profiles to the
correct length and mount them on the correct side
(see Fig. 44)
•
Side 3: Cut the connection profile to the correct
length and mount it on the correct side (see Fig.
37).
•
Side 4: Cut the connection profile to the correct
length and mount it on the correct side (see Fig.
47).
•
Mount Z-profiles over the projecting cross beam
of the top section as shown in Fig. 48 of this
chapter. The plastic roof foil of the bottom casing
section can be applied over these profiles.
6 - FRESH AIR INLET HOOD
The fresh air inlet hood may be supplied loose with the
AHU. In this case the air inlet hood must be attached
in the correct position as follows:
•
Install the inlet hood with the screws supplied in
the correct location.
•
The bottom wire grille should then be attached to
the corner post.
Fig. 50 - Fresh air inlet hood
NOTE: The connection between the outdoor air
suction grille and the corner post should be sealed.
14 |
HHFlex Air Handling Units