operator
manual
REVISION: 09/2014 | page 7 of 16
Food Waste Bio-Digester
Refer to Chapter 3 of this manual, relating to safety.
4.1 INSTALLATION REQUIREMENTS
Mechline’s food waste bio-digester is delivered as a complete unit and is designed for installation on a firm flat surface in
a well-ventilated indoor location. The appliance must not be installed outside and exposed to the elements. If it’s outside;
it must be covered by a fully rain-proof shelter and protected from temperatures lower than 5°C (41°F) and higher than
40ºC (104°F).
Ensure that the designated area for the appliance is of solid construct to withstand and support the operational weight of
275 Kg (605lbs).
If the appliance is relocated or reinstalled after commissioning, Mechline must be notified. Failure to do this could
invalidate the warranty.
NOTE:
Installation must be carried out in accordance with local authority requirements. The appliance incorporates
Mechline’s WRAS-approved AB-Type air gap backflow prevention device.
4.2 PRE-OPERATION CHECKS (UNPACKING)
NOTE:
This is a minimum 2-person operation.
4.2.1 Carefully remove the cardboard sleeve that covers the appliance. Inspect the appliance for damage and inform
Mechline immediately if any damage is found. Claims for damage cannot be entertained once the appliance has
been removed from the pallet.
4.2.2 Open the appliance lid and remove the pack of 4 adjustable legs. Close the appliance lid
4.2.3 Use a 17mm (
11
/
16
inch AF) socket/spanner or wrench to remove the 4 transit fixing bolts from the underside of the
appliance’s pallet.
Cont’d...
Chapter 4. INSTALLATION INSTRUCTIONS