Installation
900285-00 12/2016
Innovative Hearth Products
DRT3000 and DRC3000 Series Direct-Vent Gas Fireplaces
20
5.
Rough in the Electrical Supply, if Needed
As necessary, rough in the fireplace electrical supply per NEC and local codes.
6.
Install the [Optional] Blower Kit before Installation in the Framing
1. Remove the left side blower cover panel screw, and blower cover panel (see Table 12, Page 17). Retain the
panel and screw for later reinstallation.
2. Slide the blower through the opening and position it with the bracket oriented to the front of the firebox and the
blower discharge to the rear of the firebox. Bend the two tabs in the firebox floor to secure the blower to the
floor.
3. Reinstall the blower cover panel and secure with the removed screw.
4. Access the blower supply wiring through the front of the fireplace and plug it into the junction box in the right,
rear of the fireplace (Figure 32).
5. Install the blower control switch according to its included instructions.
5. Installing Non-Combustible Fireboard Standoff - All Models
A non-combustible standoff board is provided for all model fireplaces to prevent overlap of drywall or other material of portions of the
fireplace that may be prone to the buildup of heat. It is supported by a middle bracket and two side brackets.
Separate and note metal side
(2) and center (1) brackets.
Step 1: Remove two screws from the top and side of the unit. Bend the side bracket securing tab
over the edge of the unit and secure. Secure bracket to the top through the clearance screw hole.
Step 2: Remove the three screws that align with the clearance
screw holes from the top of the unit. Secure the center bracket to
the top center of the fireplace.
Step 3: Top of front fireboard
standoff should be flush with
top standoffs (not shown).
Step 4: Fireboard standoff can
be secured to the capture screw
holes.