Quick User Manual
3 Commissioning
17
3.2
Commissioning Procedure
Before starting the inverter, make sure all the installation and connections are
completed and verified. Proceed as follows to start the inverter for the first time.
1.
Connect the AC circuit breaker.
2.
Connect the DC circuit breaker between the inverter and the battery pack.
3.
(Optional)
Power on the battery pack manually if a battery is equipped.
4.
Rotate the DC switch to “ON”. The DC switch may be integrated in the inverter
or installed by the customer.
5.
The LCD screen will be activated 5s later and enter the initial settings.
6.
Refer to
Fig. 3-1
for button operations and complete all initial settings
according to the procedure in
Fig. 3-2
.
7.
Check the icons on the main screen. Refer to
Tab.
5-1
for the explanations.
8.
Check the state of the indicator.
Tab. 3-2
State Descriptions of the Indicator
Colour
State
Description
Green
On
The inverter is running normally.
Blinking
The inverter is in the process of starting.
Off
Other states except Running and Startup.
(Refer to
Tab. 5-1
for state descriptions.)
Red
On
Permanent fault or upgrade failure.
Blinking
Other system faults or main alarms.
Off
No fault occurs.
9.
Visit
www.solarinfobank.com
or SolarInfo Moni APP to view inverter
information. Get the related manuals at
www.sungrowpower.com
.
If the inverter commissioning fails,
Press
to view the current errors. Remove the
existing malfunctions and then repeat starting up the inverter according to the
procedure detailed in this section.
Содержание SH3K6
Страница 1: ...SH3 6_4 6K QUEN Ver12 201710 Version 1 2 Quick User Manual SH3K6 SH4K6 Grid Connected Hybrid Inverter ...
Страница 2: ......
Страница 4: ...II System Overview ...
Страница 5: ...III ...
Страница 6: ...IV ...
Страница 7: ...V ...
Страница 8: ...VI ...
Страница 28: ...3 Commissioning Quick User Manual 18 Fig 3 2 Initial Settings ...