START UP
Start-Up Procedures
Perform the following tasks to start the Sundyne
pump.
1. Run-in of pump: If the pump is to be run
under conditions which are considerably
different from those conditions listed on the
spec sheet (such as a change in specific
gravity, suction pressure, flow rate, etc.) the
factory should be consulted to ensure that
the run-in conditions are compatible with the
pump.
2. Check to ensure that the driver has been
serviced per the instructions provided by the
driver manufacturer.
3. Auxiliaries - Check utility connections; verify
that auxiliary piping is per Sundyne
drawings; verify switch and instrument
connections and set points; calibrate flow
instruments and other transmitters.
4. Flushing screens should be installed in all
field assembled piping connections.
5. Check the pump specification sheet and
outline drawings for seal environment
requirements. Be sure that the seal housing
port piping is properly connected. If double
seals are used, buffer fluid must be
pressurized before suction pressure is
applied to the pump. Seal Drain must be
open to atmosphere. Maximum allowable
backpressure is 5 psig (0.35 kg/cm²). If no
seal flush is used, it is recommended that a
hand bleed valve be installed at this
location.
6. Bleed air and vapor from seal before
starting.
7. Jogging is used to verify proper direction of
rotation for the main driver to the markings
on the pump case.
Note: Never start the pump against a closed
discharge valve. Always check to
ensure that the discharge valve is
partially open.