![Sun Microsystems StorageTek 9985V Скачать руководство пользователя страница 153](http://html.mh-extra.com/html/sun-microsystems/storagetek-9985v/storagetek-9985v_manual_1393025153.webp)
Delivery Requirements
The customer site must accommodate the delivery and movement of the equipment to the
installation location in the data center.
The delivery requirements for Universal Storage Platform VM installation are:
■
Dimensions:
The loading bay, hallways, doors, elevators, and stairs must be large enough to
allow the delivered equipment to be moved to the installation location.
The shipping crate dimensions are:
Height: 84 inches (2.134 meters) (overall height including palette)
Width: 42 inches (1066.8 mm)
Depth: 55 inches (1397 mm)
See Service Clearance, Floor Cutout, and Floor Load Rating for the dimensions of the USP VM
product (uncrated and unpacked).
See Dimensions and Weight for the dimensions of the USP VM components.
■
Weight:
The floors, elevators, stairs, and ramps must be able to support the weight of the
delivered equipment as it is moved to the installation location. Spreader plates may be required
to distribute the load and/or protect the floor as the equipment is moved to the installation
location.
The weight of the delivered equipment depends on the storage system configuration. The weight
for a maximally configured storage system could reach 1600 or 1700 pounds (726 to 771
kilograms).
See Dimensions and Weight for the weight specifications for the Universal Storage Platform VM
components.
Just the Facts
October 2007
153
Sun Confidential – For Internal Use and Authorized Partner Use Only
Содержание StorageTek 9985V
Страница 174: ...Just the Facts October 2007 174 Sun Confidential For Internal Use and Authorized Partner Use Only ...
Страница 175: ...I Just the Facts October 2007 175 Sun Confidential For Internal Use and Authorized Partner Use Only ...
Страница 176: ...Just the Facts October 2007 176 Sun Confidential For Internal Use and Authorized Partner Use Only ...