SPP id: Version 14 > / 131130 / Replaces 130131 / en /
N31571
/ 4 / Page 13 (19)
Series
2.15
INSTRUCTIONS
November 2013
Page
ISO
G
COPYRIGHT © SULZER PUMPS FINLAND OY
ORIGINAL INSTRUCTION
USER'S MANUAL – AHLSTAR
Installation at the site
Fig. 14,
Baseplate for pump and motor, Rectangular (STD)
Pump mounting sizes 5J, 5K, 5L, 63, 64, 65, 66, 67, 68, 74, 75, 77, 78, 79, 7A, 7B, 7C,
7D
Installation using chemical foundation screws
The foundation screw holes are drilled according to the dimensional drawing of the pump. The recommended
accuracy for the location of the holes is ±10 mm. Roughen the holes. Clean the holes well by brushing and blasting.
Install the ampules into the holes. Install the foundation screws (918.61) by hammering to the bottom of the holes
and turn them a couple of rounds. Let the glue of the ampules harden. The screws can be loaded according to the
following table.
Table 5, Chemical foundation screws
Ambient temperature
C
Time of hardening
Time for load
> +20
10 min
2 h
+10
20 min
4 h
0
60 min
10 h
min -5
5 h
28 h
Lift the preinstalled pump and baseplate and fix it into the foundation screws by two nuts (2 pcs). Adjust the position
of the baseplate before grouting by turning the hexagonal nuts of the foundation screws until assembly lies
horizontally and at the correct height.