Wrenches 1/2", 5/8”, 3/4", 15/16” , 7/8” , 1-1/8”, 1-1/16”, 13/16”, 9/16”
Crescent Wrench large
Concrete hammer drill, with 1” concrete bit & “Powers Wedge Bit 5/8”
Crow bar
5 LB sledge hammer
Large rubber mallet
3’ level
Safety:
The Hide-Away Shelter components are very heavy and proper lifting equipment & methods
need to followed at all times to insure safety. Please review the OSHA safety requirements at
http://www.osha.gov/doc/outreachtraining/htmlfiles/mathan.html
Installing the Shelter:
Confirm concrete surface is smooth and relatively level. Be sure no off-set
“bumps” are in the area of the shelter.
2 MOD Hide-Away has 2 back wall sections & 1 front wall section plus the door & frame.
3 MOD Hide-Away has 3 back wall sections & 2 front wall sections plus the door & frame.
Position the right wall section at the location customer has selected.
Position the center back wall sections to the left of the first section, insert the ¾” bolts through
the panel frame to connect the two sections together (tighten loosely at this time).
Position the left wall section to the left of the back center wall and loosely tighten with ¾”
bolts.
Position the door & hinge to the front section and side wall, and attach using 3/4” bolts.