The Geareducer vent or vent line must be checked for blockage 
to prevent failure of pinion shaft oil seal—clean when necessary. 

Long-Term Storage or Downtime 

indefinite duration

If unit has been in an operational state, perform a 

Run Cycle 

and drain the oil including volume in the oil line, if equipped. If in  
storage, unit does not need to be operated.
Fabricate and install an overflow reservoir system and fill unit 
entirely full of oil. 

Maintenance Cycle

  If unit is stored outdoors, drain condensate 

monthly and top off oil as necessary. If unit is stored indoors, 
but not climate controlled, maintenance cycle may be extended 
to 3 months. If stored in climate controlled space, cycle may be 
extended to once per year.
See 

Marley User Manual Z0238848

 

“Cooling Tower Downtime 

Instructions” 

and 

Marley Drawing Z0544916

 

Marley Geareducer 

Reservoir System”

 for further information. 

Inspection Of Internal Parts

Remove the inspection cover plate from the side of the Geareducer 
case at each oil change. Check inside of Geareducer for cleanliness 
of case and internal parts. If any sludge is present, flush inside of 
Geareducer and connecting oil line.
Also at this time, observe the contact pattern of the gear teeth to 
see if they appear as illustrated in 

Detail A

 and 

B

. If incorrect gear 

tooth pattern should occur, refer to 

Marley Field Repair Manual 

for Series 32.2 Geareducer.

Repair and Overhaul

Geareducers can be repaired in the field, however, ma jor repairs 
require the use of a fully equipped machine shop. If field repair or 
overhaul is preferred, refer to Geareducer Parts Manual sheets for 
parts required. Field repair instructions are available from Marley on 
re quest. Contact the Marley sales office or Marley repre sentative 
in your area for information.

operation and service

Figure 1  

Priming Interstage Shaft

Check all gasketed joints for oil seepage. Tighten cap screws and 
flange bolting if necessary.
The Geareducer must be installed level and properly aligned 
with the driveshaft and motor shaft. Refer to the 

Driveshaft 

User Manual.

It is recommended to operate the Geareducer for no less than 
30 minutes in any given run sequence. It is acceptable to ignore 
this when “bumping” the motor for confirmation of the correct 
direction of rotation.

Seasonal Shutdown 

up to 4 months

At start 

of shutdown period, perform a 

Run Cycle

 and change the 

oil. See section on 

Service and Lubrication.

Every 2 weeks

 

check the oil level and perform a 

Run Cycle.

Once each month

 drain any water condensation from the lowest 

point of the Geareducer and its oil system. Check the oil level and 
add oil if necessary. Perform a 

Run Cycle.

To put back into operation

, drain water condensation from the 

lowest point of the Geareducer and its oil system and check oil 
level. Add oil if necessary.

Содержание Marley Geareducer 32.2 Series

Страница 1: ...Geareducer model 32 2 INSTALLATION OPERATION MAINTENANCE Z0238997_B ISSUED 09 2016 READ AND UNDERSTAND THIS MANUAL PRIOR TO OPERATING OR SERVICING THIS PRODUCT user manual...

Страница 2: ...ed via the filler neck or pumped in through the drain connection this lubricant will not reduce the overall level of protection however if the unit is operated for any amount of time the Pre Commissio...

Страница 3: ...should occur refer to Marley Field Repair Manual for Series 32 2 Geareducer Repair and Overhaul Geareducers can be repaired in the field however ma jor repairs require the use of a fully equipped mac...

Страница 4: ...4 Detail A Spiral Bevel Gear Tooth Pattern Detail B Helical Gear Tooth Pattern operation and service...

Страница 5: ...used oil in an appropriate container 2 With Geareducer drained the three way valve turned clockwise and the pipe plug removed connect fill source either a street ell and stand pipe of sufficient lengt...

Страница 6: ...perating unit check all gasketed joints for oil seepage Tighten flange bolts if necessary Check the oil level placard location each time the oil is changed The full mark on the placard must be at the...

Страница 7: ...re Air Temperature at Geareducer Below 110 F 43 C Above 110 F 43 C ISO 150 ISO 220 operation and service Maintenance Service Monthly Semi annually Seasonal Startup or Annually Geareducer Drive Inspect...

Страница 8: ...n the interest of technological progress all products are subject to design and or material change without notice Geareducer 32 2 US E R MAN UAL SPX COOLING TECHNOLOGIES INC 7401 WEST 129 STREET OVERL...

Отзывы: