background image

 

 

 
 
 
 
Before  you  install  the  windgenerator  on  a  mast  construction  make  sure  that  the  3-
phase wiring is disconnected from the charge regulator or fix one blade so that the 
system cannot turn. You can also connect the 3 AC wires to block the system whilst 
mounting. Another possibility to install the system is to screw the hub with the blades 
to the shaft at the very end of the mounting procedure. The mast must be well fixed 
so that it is safe in strong wind and sea conditions. Please ask a professional who is 
able to assess the load that the system generates in strong wind conditions. 
 
 

2.2.   Elecrical risks 

 
An idle running windgenerator can generate an AC voltage of 40 volt AC /15amp per 
phase. Only connect all components if you are familiar with electric wiring. The high 
voltage can cause serious injuries and fire if you do not pay attention to safety. Never 
ever  touch  the  open  end  of  the  wires.  The  currents  on  charging  the  batteries  can 
reach  more  than  30  A  DC.  The  whole  wiring  electric  components  and  connection 
points must be able to carry a current of 40 A. Find information about suitable cable 
dimensions on page 9 
 

Warning

 

Wires with insufficient diameters can cause fire. 
 
Make  sure  that  the  wires  are  run  so  that  mechanical  damages  cannot  occur.  A 
damaged cable is a severe safety risk. Install a fuse to the batteries positive pole as 
closel  as  possible  to  the  battery.  In  any  case  a  short  circuit  of  the  poles  must  be 
avoided. 
 

Warning:

    

A short circuit can cause fire and explosion. Never ever install batteries where sparks 
can cause this risk. Always ensure sufficient ventilation! 

 

The  electrical  installation  should  be  carried  out  by  persons  with  suitable  skills  who 
know  what  they  do.  Before  a  storm  the  Silentwind  generator  should  be  manually 
stopped  with  the  stop  switch  on  the  charge  regulator.  In  case  of  storms  we 
recommend to fix one rotorblade to the mast because of the risk of flying objects. 
 

Содержание Silentwind

Страница 1: ...instructions for use installation manual SILENTWIND...

Страница 2: ...ailability of electric energy without the possibility of grid connection is essential Fair winds at any time The Spreco Team Please note that this manual is part of the product and must be read closel...

Страница 3: ...nical data 7 3 3 Dimensions 7 3 4 Power diagram 8 4 List of enclosed parts 8 5 Operation description 9 6 Diameters of cables 9 7 Installation 9 8 Getting started 11 9 Run and stop 12 10 Charging indic...

Страница 4: ...d carbon fiber blades were successfully tested in a wind tunnel up to wind speeds of 35m s 63 knots according to DIN EN 61400 2 Therefor you need not worry about the Silentwind generator in any storm...

Страница 5: ...Never ever touch the open end of the wires The currents on charging the batteries can reach more than 30 A DC The whole wiring electric components and connection points must be able to carry a current...

Страница 6: ...C Rated power 400 Watt Rated peak power at 13 5 m s Start up speed 2 2 m s Start of charging 3 m s Charge indicator Blue LED on the buttom of housing 3 1 2 Mechanical date Safety test in wind tunnel 1...

Страница 7: ...ge 12 24 VDC Max input current windgenerator 30 A Max input current solar 10 A 100Wp LCD LED displays W V A kWh Ah load data 3 2 2 Mechanical data weight 1 15kg regulator Package dimensions 190x120x65...

Страница 8: ...parts All information is reliable The producer does not take any resonsibility for inaccuracies The user of both the instructions and the product takes any responsibility and any risk All specificatio...

Страница 9: ...equivalent of sonic velocity at the tips of the blades For every day use and safety reasons we have equipped the charge regulator with an additional electronic and manual stop switch 6 Diameters of c...

Страница 10: ...ice Once the mast is mounted you can start the relatively simple installation of the Silentwind generator First connect the 3 CF blades to the assembly hub see page 17 sketch 4 with the enclosed srews...

Страница 11: ...ntrolle Mast construction Optional check according to instruction especially all srew connections bracing vertical position Grounding and lightning protection according to local regulations Electric i...

Страница 12: ...ator A blue LED at the bottom of the body shows you when the charging process starts This depends on the state of charge of the battery normally 12 5 volt Attention If you operate the system with a 3...

Страница 13: ...bearings as to free movement bearing play and watertightness Deficient bearings must be replaced 11 4 Corrosion protection The complete housing is made of seaworthy alumine and additionally powder co...

Страница 14: ...th instruction Generator shaft sluggish Turn manually Connection windgenerator charge regulator short circuit of AC cables short circuit of generator customer service Windgenerator doesn t charge Poss...

Страница 15: ...iences Charge regulator wrongly installed Check in line with manual Correct installation Charge regulator stop switch is in position stop Switch stop switch in position RUN Observe manual instructions...

Страница 16: ...16 14 Attachment sketches sketch 1 sketch 2 sketch 3...

Страница 17: ...17 sketch 4 sketch 5 sketch 6 sketch 7...

Страница 18: ...18 sketch 8 sketch 9 sketch 10 sketch 11...

Страница 19: ...ill have to prove that the windgenerator has been mounted to an appropriate mast construction Damages caused by acts of nature beyond control Spreco Lda cannot be held responsible for especially light...

Страница 20: ...20 Notice...

Страница 21: ...rialnumber windgenerator Seriennummer Laderegler Serialnumber charge controller Verk ufer Firmenstempel Unterschrift Purchaser company stamp signature Kaufdatum date of purchase Die genauen Garantie B...

Отзывы: