7
Commissioning
7 Commissioning
7.1 Filling in the type plate
Tool:
•
Permanent marker
►
Mark off the correct battery capacity and nominal power on the type plate of
the storage system.
The type plate is located on the outside of the storage system. The battery capacity
and nominal power can be determined from the technical data (see 3.1 - p. 13).
7.1.1 Taking photos to document installation
The photo upload is obligatory for both offline commissioning and online com-
missioning.
To fully document the installation, photos of the finished installation must be taken
and send to sonnen.
1. Take the described photos of the storage system (see appendix of the document).
2. Go to the following website: sonnensupportaustralia.com.au
3. Navigate to ‘Reference’ and ‘System Commissioning’.
4. There the photos can be uploaded, using the procedure described.
5.
Alternatively
the photos can be send to the following e-mail address:
7.2 Filling in the commissioning report (optional)
Paper form only necessary when commissioning without an internet
connection
Thanks to the commissioning assistant 2, it is no longer necessary to complete and
send the commissioning report in paper form.
►
Only carry out the following steps if the commissioning assistant displays a
corresponding message.
►
Complete the commissioning report in the appendix of the document in full.
►
Make a copy of the filled in commissioning report, the original remains with the
operator.