SolarWorld Sunfix Bisun Скачать руководство пользователя страница 1

Instruction sheet

www.solarworld.com

MOUNTING SYSTEM FOR SOLAR POWER 

SYSTEMS  

PLANNING AND DESIGN

Original instruction sheet for installers

Содержание Sunfix Bisun

Страница 1: ...Instruction sheet www solarworld com MOUNTING SYSTEM FOR SOLAR POWER SYSTEMS PLANNING AND DESIGN Original instruction sheet for installers...

Страница 2: ...s smoothly all components selected and used in the mounting system are of the highest quality The following instructions describe the correct installation of the based on an example This should help y...

Страница 3: ...se 8 B2 Technical overview 9 B3 System construction 10 Installation example C1 Defining the system position 13 C2 Roof area measurement 14 C3 Placing supports 15 C4 Module installation 16 C5 Installat...

Страница 4: ...njury f f Carefully store instruction sheet Warning signs signal word Warning levels DANGER Warns of imminent death WARNING Warns of possible death and or serious injury CAUTION Warns of possible pers...

Страница 5: ...rikes them When breaking a connected string of modules e g when disconnecting the DC line from the inverter under load a dangerously strong arc can occur Note the following f f Never remove the solar...

Страница 6: ...If you have any doubts consult a specialist e g stress analyst technical expert f f Protect outdoor cables against weathering UV light and mechanical damage with suitable measu res for example by layi...

Страница 7: ...he ground from falling objects f f Also follow the safety instructions of all other system components e g inverters and modules f f Only have the system connected to the public grid by a qualified ele...

Страница 8: ...instruction sheet Improper use This list does not include all conceivable types of improper use and thus does not claim completeness The advice provided is only intended to convey a sense of improper...

Страница 9: ...f Module tilt 10 f f Minimum size per module array 3 x 3 modules f f Maximum size per module array 10 x 10 modules f f Standard static friction values Membrane roof with rubber mats foil laminated 0...

Страница 10: ...10 10 B3 System construction Fig B 3 1 Detail 1 Fig B 3 1 Detail 2 Fig B 3 1 System construction A B 3 6 4 B A 5 7 4 3...

Страница 11: ...Fig B 3 1 Detail 3 Sunfix Bisun component list 1 Module 2 Front rack 3 Connecting rack 4 End rack 5 Ballast tray 237 cm x 30 cm 6 Ballast stone e g paving slab 30 cm x 30 cm 7 Heavy load rail C 2 C 1...

Страница 12: ...12 12 Dimensions system construction For reference only Fig B 3 2 System construction Fig B 3 3 System construction side view...

Страница 13: ...the system on the roof in the direction of the eaves may occur This is relevant for roofs with a tilt angle of 3 or more In this case the system must be secured against long As a rule all work underta...

Страница 14: ...ec ted Then a new generator array must be started in each direction 1 Before beginning installation the roof must be measured according to planning documents and the first point of installation must b...

Страница 15: ...with a ballast 2 Place the connecting supports and measure the distance to the front supports The connecting supports can still be repositioned in the course of tray To protect the roof membrane four...

Страница 16: ...tigh ten the module clamps with 10 Nm f f Beginning with the second module before placement the cables are attached to the plug Torque force MA 10 Nm Driver for module clamping 5mm allen key connectio...

Страница 17: ...y results and the installation process is repeated as from Fig C 3 2 In the final back row the end supports are placed and ballast is again added according to planning specifications The number and po...

Страница 18: ...ecome applicable to sup port the modules If your project documentation reflects the application of heavy load rails two rails per module are to be attached to each long side of the frame Make sure tha...

Страница 19: ...19 19 C7 Placing ballast stones Fig C 7 1 Fig C 7 2 Fig C 7 4 Fig C 7 3 Fig C 7 5 NOTE Ballast should be evenly distributed...

Страница 20: ...ction of the multi string solar generator by measuring the open circuit voltages of the individual strings 2 Comparethemeasuredvalueswiththespecifications Values deviating from the specifications are...

Страница 21: ...ommended for PV module frames Connect all electrically conductive parts with each other by appropriate means and then connect them to the equipotential busbar with at least 6 mm copper X X External li...

Страница 22: ...f Since observance of these installation instructions and the conditions and methods of installation operation use and maintenance of the Sunfix Bisun mounting system can not be checked or monitored b...

Страница 23: ...23 23 D Notes...