1. Access the Status screen:
a. If not already ON - turn ON AC to the inverter by turning ON the circuit breaker
on the main distribution panel.
b. Open SetApp and follow the instructions on the screen (scan the inverter bar-
code; move the ON/OFF/P switch to P position (for less than 5 sec) and release).
The mobile device creates a Wi-Fi connection with the inverter and displays the
main Commissioning screen.
Status
Inverter
SN 07318000C
Power
Voltage
Frequency
Optimizers
Connected
S_OK
Server Connected
Status
Production
Switch
ON
CosPhi
1.00
Limit
No Limit
Country
Netherlands
Voltage
Temp
Fan
Commissioning
2. Check that
S_OK
-
Server Connected
status appears in the main inverter section.
3. Scroll down to the Communication section and check that the communication
options are as required. For more information refer to
Communication
LAN
Connected
RS485-1
Modbus
2 of 2
RS485-2
SE Slave
None
Cellular
N/A
Wi-Fi
NC
ZigBee
NC