Site Production:
The meter is installed at the inverter output and reads the
energy produced by inverters at the site.
Ext. Production
: The meter is used for export limitation with 3rd party generators
and for AC coupling with non-SolarEdge inverters.
6. Select Meter Protocol, and select SolarEdge.
7. Select
Device ID
and enter the Modbus address corresponding to the ID DIP switch
settings on the meter.
8. Select
CT Rating
and enter the current transformer's rating in amperes.
9. Select Grid Topology and select Wye.
10. If relevant, select PT Scaling and set the potential transformer ratio. The default
value is 1.
To verify the meter connection using SetApp:
1. From the SetApp main menu, select Status.
2. On the Status page, scroll down to the Communication section and view the current
connection state.
Meters
Export Meter
RS485-2
Modbus ID #1
Status
OK
Power
7.60 kW
Energy
13.68 MWh
Device Configuration using the Device Display Menus
To operate the SolarEdge device menus:
Use the four user buttons to control the LCD panel menus:
Esc
: Moves the cursor (>) to the beginning of the currently displayed parameter;
goes to the previous menu, and cancels a value change with a long press (until
Aborted
is displayed).
Up
(1) and
Down
(2): Moves the cursor from one menu option to another, moves
among the characters of a displayed parameter, and toggles between possible
characters when setting a value.
Energy Meter with Modbus Connection MAN-01-00270-1.3
22
Device Configuration
Содержание SE-MTR240-NN-S-S1
Страница 1: ...Installation Guide Energy Meter with Modbus Connection For North America Version 1 3...
Страница 47: ......