5. Commissioning of inverter
5.1. Safety inspection before commissioning
Ensure that DC and AC voltages are within the range permitted by
the inverter.
Attention
5.2. Start inverter
Step 1
Turn on DC switch.
Step 2
Turn on AC switch.
When the solar arrays generate adequate power, the inverter will startup
automatically. Display showing “normal” indicates correct operation.
Step 3
Choose the correct country code. (refer to section 6.3 of this
manual)
Notice: Different distribution network operators in different countries have
different requirements regarding grid connections of PV grid connected
inverters.
Therefore, it's very important to make sure that you have selected the
correct country code according to requirements of local authority.
Please consult qualified electrical engineer or personnel from electrical
safety authorities about this.
Shenzhen SOFARSOLAR Co., Ltd. is not responsible for any
consequences arising out of incorrect country code selection.
If the inverter indicates any other fault, please refer to part 7——error messages for help.