![Sofar solar 3.3K- 5.5KTL-X Скачать руководство пользователя страница 26](http://html.mh-extra.com/html/sofar-solar/3-3k-5-5ktl-x/3-3k-5-5ktl-x_user-manual_1311971026.webp)
SOFAR 3.3K~12KTL-X
User manual
All rights reserved
©
Shenzhen SOFARSOLAR Co ., Ltd.
- 21 -
the S phase CT S1 (red) received the meter position. 4, position. 6 S2 (black)
received the meters, S1 (red) of CT connected with T is connected to electricity
meter position. 7, S2 (black) is connected to electricity meter position. 9.
NOTE: The direction of the current transformer is shown in fig.
④
①
②
③
④
Generation and Export Limit Control functions for the inverter are available but
require the use of an external measurement device to obtain grid information.
The way to obtain grid information:
Plan A: Meter + CT
Note: CT and Meter is supplied separately to the inverter. Contact
manufacturer/importer/distributor to order CT and Meter.
To obtain grid information via Plan A:
Wiring according to the wiring method as shown in "Figure 4-5”, and enable
Anti-Reflux Power function and set the Reflux Power limit on the menu interface of
the machine. Refer to <6.3 Main interface in this manual for specific operation
methods.
The setting of hard anti-reverse flow is the same as that of Plan A. The electricity
meter function will also need to be enabled via the menu interface of the machine.