Special precautions
• The unit is heavy: wear safety shoes and preferably use a vacuum lifter for
handling operations.
• All handling operations will require at least two people (unpacking, lifting,
installation in a rack system).
• Before and after the installation, if the UPS remains de-energised for a long
period, the UPS must be energised for a period of 24 hours, at least once every
6 months (for a normal storage temperature under 25°C). This charges the
battery, thus avoiding possible irreversible damage.
• For three-phase AC input installation, this equipment complies with IEC
61000-3-12 provided that the short-circuit power Ssc is greater than or equal
to 2.97MW at the interface point between the user’s supply and the public
system. It is the responsibility of the installer or user of the equipment to ensure,
by consultation with the distribution network operator if necessary, that the
equipment is connected only to a supply with a short-circuit power Ssc greater
than or equal to 2.97MW.
• During the replacement of the Battery Module, it is imperative to use the same
type and number of elements as the original Battery Module provided with the
UPS to maintain an identical level of performance and safety.