background image

 

 

ROOF  ASSEMBLY 

11 

SELECT: 

 

3 x 1.720 Roof Sheets 

1 x 1.550 Spouting 

2 x 1.720 Barges 

20 x 40mm Weatherseal Nails 

22 x Rivets 

STEP 1: 

 

 

Ensure Shed is sitting level and square. 

 

 

Lay Roof Sheets on the Top Plates (with slots at front). 

 

 

Rivet sheets together at overlaps with 2 x rivets per join

.

 

STEP 2: 

 

 

Position the Roof Sheets with front overhang of 130mm at each 
end (

fig. 1

). 

 

 

Using 4 x 40mm weatherseals, nail the Roof Sheets to the Top 
Plates at each corner, ensuring ribs on the Roof Sheets line up with 
ribs on the Wall Sheets (

fig.2

).

 

STEP 3:

 

 

 

Ensure the Front and Back Top Plates are straight. Nail the roof 
sheets to the front & back Top Plates, using 1 x nail per pan (

fig.2

). 

STEP 4: 

 

 

 

Place barge flashings on roof at end of shed ensuring the diagonal 
trimmed end is at the front. 

 

 

Rivet the Barge Flashings to the roof and the side wall, using four 
rivets on top of barge and four into the side (

fig.3

).

 

fig.2 

fig.3 

X 4 

X 4 

Barge

 

IMPORTANT—FOR SHEDS WITH OPTIONAL CLEAR 

ROOF PANEL 

 

Assemble as below, making sure that the Clear Roof Sheets 
overlap the standard roof sheets on both sides.  
The Clear Roof Panel must be secured to the front and back 
Top Plates. Pre drill and fasten with the 40mm weatherseal 
nails provided.

.

 

SIDE 

WALL 

FRONT 

WALL 

BACK WALL 

SIDE 

WALL 

BOTTOM PLATE 

TOP PLATE 

130mm 

fig.1 

130mm 

STEP 5:

 

 

 

Place spouting in position and rivet to Barge Flashings at each end 
and rivet to roof sheets (1 rivet per 1 sheet). 

Содержание SS1515

Страница 1: ...ASSEMBLY INSTRUCTIONS SS1515 BASE SIZE 1 520m x 1 520m...

Страница 2: ......

Страница 3: ...r cladding used in Smart Store Sheds Wash all surfaces annually using a hose and soft nylon brush Within 2 km of coast wash every 3 months as above After a storm wash the cladding and the gutters as s...

Страница 4: ...3 Door Brace 1 255 m 2 Door 3 4 Sheet 1 850 m 2 Barge 1 720 m 2 TIMBER Padbolt Support 0 140 m 1 Bottom Plates H4 Green Front Back 1 520 m 2 Spouting 1 550 m 1 Bottom Plates H4 Green Sides 1 520 m 2...

Страница 5: ...ont Bottom Plate Side Back Wall Sheets Front Wall Sheet Door Jambs Door Sheets Door Side Flashings Padbolt Support Flashing Hinge Door Brace Door Top Bottom Channel QUICK OVERVIEW 1 LAY FOUNDATION 2 A...

Страница 6: ...coming through from underneath During construction you may raise the bottom timber plate to allow the wall cladding to protrude 20mm below the bottom plate This will stop water flowing between the bot...

Страница 7: ...fig 1 Rivet sheets together STEP 2 Position door side flash ings and assemble door as shown Drill and rivet as per dia gram ensuring rivets penetrate into door sheet STEP 4 Rivet door brace flashings...

Страница 8: ...ing each side of wall sheets overhangs the end of Bottom Plate by 15mm Check that the distance between the Top and Bottom Plates is correct As per diagram in step 1 Check that the Bottom Plate is stra...

Страница 9: ...e wall sheets overhang the Top Plate by 15mm as shown Check that the Top Plate is straight then nail wall sheets to the Top Plate using two clouts per pan STEP 4 Nail the wall sheets to the Bottom Pla...

Страница 10: ...properly then fit remaining rivets STEP 3 Place 1 x Wall Sheet on timber plates and rivet the sheets together as shown Ensure that the top of the sheet is flush with the top of the Top Plate and that...

Страница 11: ...s while they are screwed together Before fixing ensure that the Side Panel overlaps the Back Panel Using 4 x 40mm screws 2 per join screw the Top and Bottom Plates together in the corners STEP 2 Repea...

Страница 12: ...s to the front back Top Plates using 1 x nail per pan fig 2 STEP 4 Place barge flashings on roof at end of shed ensuring the diagonal trimmed end is at the front Rivet the Barge Flashings to the roof...

Страница 13: ...to the Bottom Plate and the concrete slab A 10mm masonry drill bit is required OPTIONAL SENTRY FLOOR Position the Floor Joists equally between the side Base Plates and skew nail each end with two 75mm...

Страница 14: ......

Страница 15: ...s less than 200g m2 as published by Branz Warranty certificate being returned to manufacturer within 21 days of purchase together with proof of purchase This warranty does not cover the following Fast...

Отзывы: