5
24VDC
connections to
SRU board IOs
120VAC
connections to
DIN Rail
terminals
Emergency
brake
power
Temporary Run Stop Switch
Enable
CONSTRUCTION –
(Sheet 1: Construction)
The following instructions are from the job drawings: “Sheet 1 –
Construction”. Refer to the job’s specific drawings for connections.
Construction Box (Sample)
24v DC connections
Install jumpers between M24 and the IOs listed on “Sheet 1:
Getting Started – Construction”.
Install jumpers between M24 any additional IO’s (if required):
* Pre-Transfer
* Emergency Power
* Governor
IMPORTANT! REMOVE FACTORY WIRES ON INPUTS 521/522
o
Install the Run Bug Up/Down Switch to IO’s 521/522
Install the Run Bug Up/Down Enable switch to M24
120v AC connections
Install the temporary run switch between 120 and terminal SF1
and 120 to THL/MHL/BHL terminals on the DIN rail.
Install a jumper between EB and the terminal listed on the
drawings on “Sheet 1: Getting Started – Construction”.