SB1700-11:SE2006
Page 27
5.3 Startup
You can start up the Sunny Boy 1700 when
• The lid is securely screwed on the enclosure.
• The AC (mains) cable is connected correctly
• The DC cables (PV strings) are fully connected and the unused DC plug
connectors on the bottom of the enclosure are closed with the protective caps
How to start up the inverter
Check the string voltages again to make sure they are within the limits stated in
section 4.2 "PV generator requirements" (page 15).
If the Sunny Boy still indicates a too high DC voltage even though the voltage is within
the specification contact
SMA
Technologie AG (see section 10 "Contact"
1.
Switch the line circuit breaker to the "on"
position.
2.
Now look at the LED display and check the table
on the next page to check whether the Sunny
Boy 1700 is in a fault-free operating status
If the bottom yellow LED flashes four times at intervals of one
second, the grid voltage and the PV generator must be
disconnected from the Sunny Boy 1700 immediately! There is a risk
of damage to the inverter resulting from excessive DC input
voltage.
On!
Off
Содержание SUNNY BOY 1700
Страница 2: ......
Страница 6: ...SMA Technologie AG Page 6 SB1700 11 SE2006 Installation Guide...
Страница 8: ...Foreword SMA Technologie AG Page 8 SB1700 11 SE2006 Installation Guide...
Страница 10: ...Safety information SMA Technologie AG Page 10 SB1700 11 SE2006 Installation Guide...
Страница 30: ...Opening and closing the Sunny Boy SMA Technologie AG Page 30 SB1700 11 SE2006 Installation Guide...
Страница 38: ...Replacing the varistors SMA Technologie AG Page 38 SB1700 11 SE2006 Installation Guide...
Страница 42: ...Rating for a line circuit breaker SMA Technologie AG Page 42 SB1700 11 SE2006 Installation Guide...
Страница 44: ...Contact SMA Technologie AG Page 44 SB1700 11 SE2006 Installation Guide...
Страница 45: ......
Страница 46: ......
Страница 47: ......