Inspection on Machine 

Inspect the whole machine to find: 

 

 

Crack in a weld joint or structural part 

 

Machine dent or damage 

 

Severe rust, corrosion, or oxidation 

 

Ensure that all the structural parts and other key 

components  are  complete,  and  all  the  relevant 

fasteners  and  pins  are  correctly  positioned  and 

securely tightened. 

 

Prop up the side column of platform and install 

safety pin with wirerope 

 
Inspection on Hydraulic Oil Level 

 
 
 

Keeping  the  hydraulic  oil  in  the  right  oil  level  is 

critical to machine work. If the hydraulic oil is in an 

improper oil level, it will damage the hydraulic parts. 

Through daily inspection, the inspector can determine 

the changes of hydraulic oil level, which can indicate 

the problems in the hydraulic system. 

 

Perform the following procedures  when the platform 

is retracted. 

 

1.

 

Open the right door, and make visual inspection 

on flank of hydraulic oil tank 

 

 

Result:  Hydraulic  oil  level  should  be  between 

“add” and “full”. 

 

2.

 

Refuel as needed and do not overdo. 

 

Hydraulic Oil Mark                             

 

Normal temperature region (from 0

℃ 

to 40

℃)

L-HM46;   

 

Cold region (from -25

℃ 

to 25

℃)

: L-HV32; 

 

High temperature region: (

40

℃)

: L-HM68; 

 

Extremely  cold  region:  (

-30

℃)

:  Special 

schemes need confirmation: 

 

Different  hydraulic  oil  can  be  added  according 

to  customer’s  requirements  before  leaving 

factory. 

 

Inspection on Storage battery 

 
 
 

Warning:  The  storage  battery  condition  is  very 

important  to  good  machine  performance  and  safe 

operation.  Improper  liquid  level  of  electrolyte  or 

damaged cable and wiring may cause damage to parts 

and dangerous conditions. 

 

Hazard  of  electric  shock; 

contact  with  electrical  circuits 

can  cause  death  or  serious 

personal  injury. Remove all rings,  watches and  other 

accessories. 

 

Hazard  of  personal  injury;  the 

storage  battery  contains  acid. 

Avoid  the  overflow  of  or 

contact with the acid in the storage battery. Use soda 

water to neutralize the spilled storage battery acid. 

 

This  inspection  is  carried  out 

after the storage battery is fully 

charged. 

1.

 

Wear protective clothing and protective glasses. 

2.

 

Ensure the connection of storage battery cable is 

not corroded. 

3.

 

Ensure  the  storage  battery  is  fixated  firmly  and 

the cable wiring is fastened. 

4.

 

 

Adding  wiring  end  protectors  and  antiseptic  sealants 
will  help  eliminate  corrosion  of  storage  battery 
terminals and cables. 

Function Test 

 
 
 

 
 
 
 
 
 
 
 
 

 

Do not operate, unless:

 

 

You  have  mastered  and  practiced  the  safe 

machine operating rules stated in this Manual. 

1 Avoid dangerous situations. 

2  Always  perform  the  pre-operational 

inspection. 

3 Always perform pre-usage functional tests. 

Learn  and  understand  the  function  test 

before the next step. 

Warning 

Warning 

Attention 

Attention 

10

GTJZ1412 & GTJZ1414 

Operation Manual

Содержание GTJZ1412

Страница 1: ...0800 222 111 sales elevatedaccess co nz 021 500 486 www elevatedaccess co nz GTJZ1412 GTJZ1414 Operation Manual...

Страница 2: ...pection on Parts 9 Inspection on Machine 10 Inspection on Hydraulic Oil Level 10 Inspection on Storage battery 10 Function Test 10 Test Preparation 11 Ground Controller 11 Test Emergency Stop 11 Lifti...

Страница 3: ...2 22 Wheel span m 1 25 Turning radius Internal wheel m 0 External wheel m 2 56 Maximum allowable yawing force indoor outdoor N 400 200 Control voltage DC V 24 Platform dimensions Length m 2 64 Width m...

Страница 4: ...nner middle insert 10 Level switch 11 Warning light 12 Steering wheel 13 Protection mechanism of pot hole 14 LCD reading device 15 Ground operation panel 16 Rear wheel 17 Manual braking relief valve 1...

Страница 5: ...ry Co Ltd are meant as follows Safety warning mark It is used to prompt potential personal injuries Observe all safety prompts behind this mark for the purpose of avoiding personal injuries or death R...

Страница 6: ...ed or extended Do not use the tilt alarm as a horizontal indicator The tilt alarm on the platform will ring only when the machine is heavily tilted If the tilt alarm rings Lower the platform and trans...

Страница 7: ...use the machine as a crane Do not push the machine or other objects with the platform Do not let the platform touch the adjacent object Do not bind the platform on the adjacent object Do not put the...

Страница 8: ...hine operating Hazard of Smash and Squeezing Do not let the hands and arms close to the positions with shearing hazards No working allowed under the platform or scissors zone when safety rod is in imp...

Страница 9: ...ition and unplug the key to avoid unauthorized usage 4 Chock the wheels with wedges 5 Charge the storage battery Storage Battery Safety Hazard of Burns The storage battery contains acid Wear protectiv...

Страница 10: ...ians can repair the machine according to the manufacturer s regulations After the maintenance the operator must perform another pre operational inspection before function test According to the require...

Страница 11: ...customer s requirements before leaving factory Inspection on Storage battery Warning The storage battery condition is very important to good machine performance and safe operation Improper liquid lev...

Страница 12: ...2 Ground control bit 3 Platform control bit 4 Emergency Stop Switch 5 Direction switch of platform 6 Hour meter 1 Place the red emergency stop switch on the platform and ground to the ON position 2 Le...

Страница 13: ...wering alarm should ring Attention All tests be finished in one period Test the Steering 1 Press travel and veer buttons which shall flash 2 Press left veer button on the control handle Result Vehicle...

Страница 14: ...alarm will ring The platform and ground display should show LL 4 Lower the platform change to walking function remove work platform and wooden blocks 5 Place two pieces of wood blocks with height of 1...

Страница 15: ...d in this Manual 1 Avoid dangerous situations 2 Always perform the pre operational inspection 3 Always perform pre usage functional tests 4 Check the workplace 5 Use the machine only according to the...

Страница 16: ...the direction in which the machine is traveling Movement speed of the machine is limited when the platform is raised The state of the battery will affect the performance of the machine When the platf...

Страница 17: ...level indicator lamp Use the diagnostic reading display on the platform to determine the storage battery energy Display of electric quantity for platform Proportion Descriptio n 90 100 The battery ha...

Страница 18: ...base frame 4 Press the black brake releasing handle to open the brake valve 5 Push pull the red brake releasing manual pump handle After Machine Loading Lock the wheels to prevent the machine from ro...

Страница 19: ...platform guardrail choose the appropriate length of spreader Determine center of gravity of the machine according to the chart and picture on the page Only connect the rigging to the raised point spe...

Страница 20: ...s must be closed Read Operation Manual 2 9 101012100008 When lifting and driving the machine please close the doors of the underframe left and right chambers 2 10 101012100012 Beware of hot or high pr...

Страница 21: ...16100035 Fix device before release manual relief valve and support the wheel with wedge to avoid rolling of the machine and personal damage 1 26 101012100037 Nameplate 1 20 GTJZ1412 GTJZ1414 Operation...

Страница 22: ...21 GTJZ1412 GTJZ1414 Operation Manual...

Страница 23: ...22 GTJZ1412 GTJZ1414 Operation Manual...

Отзывы: