|  3  |          

                                                    

 

 

The BOSS.6 Enclosure is intended for the housing and wiring of up to six (6) PHI 3.8, 3.5 or 3.4 kWh deep-
cycle Lithium Ferro Phosphate (LFP) batteries, or up to six (6) PHI 2.9, 2.7 or 2.6 kWh LFP batteries. The 
Enclosure may be used with the AccESS or ExprESS fully integrated units, or as a PHI Battery enclosure for 
any other installation with SimpliPhi compatible equipment. 

When the BOSS.6 Enclosure is used with the AccESS or ExprESS fully integrated units, the additional 
Enclosure containing additional PHI batteries allows for an increased amount of available energy storage 
capacity, beyond the PHI Batteries already included in the fully integrated AccESS or ExprESS units.  

 

All PHI batteries must be fully charged BEFORE commissioning. Failure to do so will Void 
the Warranty. 

As outlined 

in the 

PHI Battery Installation Manual

batteries must always be connected in parallel (Positive 

to Positive / Negative to Negative). Any bussing used within the BOSS.6 Enclosure must be used to parallel 
the batteries only; no series connections are permitted and will destroy PHI batteries and Void the 
Warranty. More detailed connection instructions are included in later sections of this manual. 

 

 

 

2.3 - Specifications 

Review Table 1 below for BOSS.6 Enclosure specifications, including physical dimensions, Warranty period 
and technical data. 

Table 1 – BOSS.6 Enclosure Specifications 

BOSS.6 Enclosure

 

WEIGHT 

270 lbs. (122.5 kg.) Without Batteries 

DIMENSIONS 

36” W x 36”H (40” w/feet) x 16” D /  

91.4 cm W x 91.4 cm H (101.6 cm w/feet) x 40.64 cm D 

Содержание BOSS.6

Страница 1: ...SIMPLIPHI POWER INC REV020620...

Страница 2: ...Table of Contents 1 0 IMPORTANT SAFETY INFORMATION 1 1 1 Safety Instructions 1 1 2 Limitations of Use 2 2 0 Product Description 2 2 1 Introduction 2 2 2 Overview 2 2 3 Specifications 3 3 0 Installati...

Страница 3: ...celets etc and wear insulated rubber electrical gloves when installing or performing maintenance on the BOSS 6 Enclosure or the PHI battery modules contained within 5 Before assembling or using the BO...

Страница 4: ...es Warranty 10 Verify polarity at all battery module connections with a standard voltmeter before 1 energizing the system and 2 turning the PHI Battery s circuit breaker ON OFF switch to the ON positi...

Страница 5: ...the PHI Batteries already included in the fully integrated AccESS or ExprESS units All PHI batteries must be fully charged BEFORE commissioning Failure to do so will Void the Warranty As outlined in t...

Страница 6: ...ge on the receiving document before signing for receipt of the equipment Damage claims should be filed directly with the carrier Not doing so can limit your ability to claim damage of equipment with t...

Страница 7: ...S 6 Carbon Steel Enclosure 1 2 Shelf Mounted Within the Enclosure 1 3 Built in Enclosure Vent 2 7 Built in Corrosion Resistant Equipment Cooling Fan 1 8 20 Long High Strength Steel Hex Head Screw 2 9...

Страница 8: ...wo or three PHI batteries SKU numbers BB 2 and BB 3 respectively are sold separately and may be purchased from any SimpliPhi distributor https simpliphipower com distributors o The built in 5 point te...

Страница 9: ...ltraflex Blue cables with 3 8 lugs 3 Use pairs of battery cables to wire from each PHI battery to the terminal blocks 6 total 8 AWG Arctic Ultraflex Blue cables with 3 8 lugs may be special ordered di...

Страница 10: ...s The BOSS 6 Enclosure can be installed directly adjacent to the AccESS or BOSS 6 fully integrated units Ensure that any ventilation is not blocked on the sides of the AccESS or BOSS 6 units If mounti...

Страница 11: ...s masonry bolts or carriage bolts minimum diameter 3 3 Assembling the BOSS 6 Enclosure 4 Make sure all PHI battery module circuit breakers are in the OFF position Prepare the battery modules for insta...

Страница 12: ...flat washers included with cabinet 3 8 lock washers and 11 16 stainless steel hex nuts originally included on the batteries Tighten the nuts to 160 in lbs 9 Attach positive interconnecting busbars di...

Страница 13: ...ar to terminals on a SimpliPhi battery video Figure 3 Interconnecting Busbars Attach to PHI Battery Terminals Interconnecting busbars are not included with Enclosure 10 Wire the negative interconnecti...

Страница 14: ...sbars are ordered from SimpliPhi or from a SimpliPhi distributor they will come with the 3 8 flat washers 3 8 lock washers and 3 8 16 long brass hex head screws needed to secure cables to the ends of...

Страница 15: ...The cables should include 3 8 lugs to fit onto the 3 8 posts on the 5 point terminal block iii Size the battery bussing to terminal block wires according to the number of batteries connected in paral...

Страница 16: ...ore commissioning CAUTION Turn the inverter s main DC Disconnect on only AFTER ALL the built in circuit breakers in the PHI Battery bank are turned on Refer to the System Commissioning SimpliPhi batte...

Страница 17: ...mino Del Sol Oxnard CA 93030 USA 805 640 6700 info simpliphipower com SimpliPhiPower com 15 5 0 Technical Support For technical support related to your BOSS 6 Enclosure please contact us as at 805 640...