TPS4-01 Installation Instructions for:
Lighting Panelboards P2 & P3
The following instructions are for the installation of the
Siemens TPS4 01 and L1 SPD modules in Siemens P2 and P3
lighting panelboards (also for field replacement.)
Figure 5:
P2 Panel TPS4 Install
1
2
3
4
5
6
8
11
10
12
9
Item
Description
Qty.
Torque
1
TPS4
1
2
TPS4 Mounting Plate
2
3
#10-32 Hex Screw with captive washer
4
30in-lb
4
#10-24 Hex Thread Rolling Screw
4
30in-lb
5
Line Bus Connector
2* or 3
6
#1/4-20 Hex Screw w/captive washer
2* or 3
65 in-lb
7
5/16-18 x 1” Carriage Bolt
5/16-18 Believille Combo Nut
2* or 3
125in-lb
8
Neutral Lug Wire Connection
N/A
120in-lb
9
P3 Riser Bracket
2
10
a) P2/P3 125A-250A = 1/4-20 x 5/8” Thread
forming screw
b) P2 600A = 5/16-18 x 3/4” hex screw
with captive washer
2* or 3
See
Torque
Note**
11
36” #8 AWG White Neutral Conductor
1
12
#8-32 Hex Thread Rolling Screw
4
30in-lb
Figure 6:
P3 Panel TPS4 Install
Table 5: Content for Installation in Lighting
Panelboards P2, P3
Step 1) Lock off all power supplying this equipment before
working on it.
Step 2) Remove the trim and dead front (and any previously
installed TPS3 or TPS4 unit.)
Step 3) Attach TPS4 Mounting Plates (Item 2, 2 Places) to
TPS4 using 10- 32 SEM screws with captive lock washer
(Item 3). The mounting plates should be attached to the
TPS4 with the offset oriented towards the top of the unit.
Torque Screws to values listed.
Step 4) P3 Panel Install Only: Attach P3 Riser Brackets to
TPS4 Mounting Plates using 10-24 Thread Forming Screws
(Item 4). Use inside set of mounting slots on Mounting Plates.
Step 5) Install Line Bus Connectors (Item 5, 3 places) on
TPS4 using 1/4-20 SEM screws with captive lock washer
(Item 6). Tighten but do not torque to allow Bus Connector
angle adjustment.
Step 6) Position the TPS4 unit on the panel base rail so
that the TPS4 Line Bus Connectors line up with panel bus
mounting toles. Slide the unit toward the interior until
the four mounting holes line up with the four holes in
the base rail.
Step 7) P2 Panel: Fasten unit to the main bus using the
P2 Panel Carriage Bolt and Nut with captive washer
(Item 7) provided w/ P2 Panel. Do not Torque at this time.
Attach the Mounting Plates (item 2) to the base rail using
10-24 hex thread forming screws (item 4) provided as
shown in Figure 5.
Step 8) P3 Panel: Fasten unit to the main bus using the P3
Panel Bus Bolt. (Item 10) provided w/ P3 Panel. Do not Torque
at this time Attach the P3 Riser Brackets (item 9) to the base
rail using 8-32 hex Thread Rolling screws (item 12) provided
as shown in Figure #6.
Step 9) If present, connect TPS4 Neutral Connection Lug
(item 8) to Panel Neutral using 8 AWG minimum wire
(item 11). For best SPD performance, trim wire as required
to provide shortest possible route between TPS4 Neutral
connection and Panel Neutral Connection. Route wire as
straight as possible and use gentle radius on any bends.
Do not kink wire. Prevent wire from encroaching breaker
locations.
Step 10) Torque all connections to the values as specified
in Table 5 or on appropriate panel label.
Step 11) Replace dead front supports (if they had been
removed for ease of placing the SPD) by installing screws,
finger tight. Then tighten with tool. Replace trim and
dead front.
Factory assembled TPS3 and TPS4 SPD units will use
appropriate Screws or Bolt/Nut combinations depending on
the panel configuration for attachment to the bus. When
replacing SPD units in the field, re-use the hardware originally
installed and use the table as a guide for proper torque values.
NOTE: For wired installations, see details in the previous section.
* only 2 tabs for single phase modules
** Torque Note: For Item 10, see Bus Connection Tightening Torque
values on label 15-A-1043-01 inside panel board.