Mounting and Commissioning
3.1 Mounting and Connections
SIPROTEC, 6MU805, Manual
C53000-G1140-C380-5, Release date 06.2018
82
Housing Assembly
• Fix the device to the mounting brackets with 4 screws.
• Loosely screw the two mounting brackets into the rack or cabinet with 4 screws each.
• Tighten the 8 screws of the mounting brackets in the rack or cabinet.
• Connect a solid low-ohmic protective and operational ground to the grounding terminal of the device. The
cross-section of the cable used must correspond to the maximum connected cross-section but must be at
least 2.5 mm
2
.
• Establish the connections according to the circuit diagram via the screwed connections. The details on the
connection technique for the communication modules in accordance with the SIPROTEC 4 System Descrip-
tion/1/ and the details on the connection technique for the current and voltage terminals on the rear of the
device in the Sections “Current Terminal Connections” and “Voltage Terminal Connections” must be strictly
observed.
Note
When using current terminals, the mounting brackets must be used in the outmost setting to observe the stip-
ulated bending radius.
Содержание SIPROTEC 6MU805
Страница 8: ...Open Source Software SIPROTEC 6MU805 Manual C53000 G1140 C380 5 Release date 06 2018 4 ...
Страница 18: ...Introduction 1 3 Characteristics SIPROTEC 6MU805 Manual C53000 G1140 C380 5 Release date 06 2018 14 ...
Страница 74: ...Functions 2 5 Device Operation SIPROTEC 6MU805 Manual C53000 G1140 C380 5 Release date 06 2018 70 ...
Страница 160: ...Literature SIPROTEC 6MU805 Manual C53000 G1140 C380 5 Release date 06 2018 156 ...
Страница 162: ...Index 158 SIPROTEC 6MU805 Manual C53000 G1140 C380 5 Release date 06 2018 ...