Revision 04 * INSTALLATION AND OPERATING INSTRUCTIONS 8BT2 * 881-4027.9
Arrangement in the foundation detail for the control cables:
NOTE!
The drawing in fig78 is taken from “Floor drawings” table at page24.
Fig78. Floor opening for control cable
Fig79. Control cable channel
at the foundation layout
The control cables are entered to the panel from the floor opening (pos.nr.2 in fig78). Then,
they are laid down to the low voltage compartment through the cable channel (fig79).
4.3.9.3. Bus wire connection
The bus wire is the electrical connection between panels.
Plug bus wires into bus wire terminal block in low-voltage compartment.
Fig80. Front view of the low voltage cabling
4.4. Final installation work
NOTE!
Please be aware of the below table regarding to the torque values during the control
process.
The bolted copper joints
with strain washer
Control tightening
torque
M6
6.8 Nm
M8
17 Nm
M10
35 Nm
M12
60 Nm
M16
145 Nm
The bolted steel joints
Control tightening
Control cable
channel
Low voltage
compartment
Содержание 8BT2
Страница 6: ...6 Revision 04 INSTALLATION AND OPERATING INSTRUCTIONS 8BT2 881 4027 9 ...
Страница 42: ...42 Revision 04 INSTALLATION AND OPERATING INSTRUCTIONS 8BT2 881 4027 9 Fig30 1250A Assembly of Coupling bars ...
Страница 43: ...881 4027 9 INSTALLATION AND OPERATING INSTRUCTIONS 8BT2 Revision 04 43 Fig31 2000A Assembly of Coupling bars ...