Installing BQD Circuit Breakers
Into Panel
1. Disconnect and lock off all power
sources supplying this panel
2. Remove the P1 Panel trim and
dead front.
3. Make sure that the handle is at off
position before installing the
circuit breaker.
4. Select the desired circuit position.
5. If the bolt-on screw is screwed
down into the tapped hole on the
panel bus bar, unscrew and
remove the screw first, otherwise
go to the next step.
6. Engage the load side mounting of
the BQD breaker into the slot of
the top barrier to secure the
breaker position as shown in
figure 6.3 below.
7. Align the BQD line connection
hole with the tapped hole on the
panel bus bar as shown in figure
6.4 below.
8. Install and tighten the screw to
the torque requirements found on
the panel labeling.
Chapter 6
System Components
Figure 6.3
BQD 15A Breaker Side View
Figure 6.4
Installing screw into the tapped hole
BQD
Breaker
Top
Barrier
BQD
Load Side
Mounting
Holes are
aligned
BQD
Breaker
16