1.8. Additional documents relevant for the mounting
In addition to these Mounting Instructions, the following documents are required for the mounting of FS Uno:
2. Transportation, Loading and Unloading
2.1. Delivery of the components
The delivery of the components for FS Uno is carried out with an appropriate vehicle, for example
•
trucks/lorries or
•
overseas containers
2.2. Preparing the delivery
•
Provide a stable and drivable surface for the delivery.
•
Please make sure that all access roads, manoeuvring and unloading areas are suitable for trucks (up to 40 tons)
and can be used by forklift trucks and hoisting equipments.
•
Please exclusively provide trained professionals for the loading and transportation activities.
WARNING
•
Always wear protective equipment (safety shoes, hard hat, safety glasses, protective gloves and
reflective vest) when unloading the FS Uno components.
•
Besides also wear the personal protective equipment that is specified in your intra-company
regulations for the respective activity.
•
It is compulsory to monitor and supervise the complete unloading process .
•
Do not step under suspended loads!
•
Please make sure that there are no unauthorized persons in the danger area.
•
Pile-driving plan
•
Blueprint drawing / general layout drawing
•
Bill of materials / parts list
•
Delivery note
•
DIS unloading guidelines for transport in maritime containers
•
General Terms and Conditions of Sale and Supply of Schletter GmbH
•
Data sheet and instructions of the module manufacturer
Please observe all country-specific regulations and standards of the country of destination and its work
instructions!