Checking the primary volumetric flow

The supplied primary volumetric flow can be simply checked by

checking the static pressure with a Pa meter and the measuring

tube available from us as accessory. 

To this end, one end of the measuring tube fitted with a rubber

cap is pressed against the air outlet of one of the nozzles at the

primary air plenum box (see drawing) and the other end is con-

nected to the hose connection of a Pa meter.

The values read on the meter and the following formula can be

used to to determine the volumetric flow: 

V  [l/s] = Primary air flow
Ps [Pa] = Static pressure

 

The K value is taken from the following table:

Air density:: 

ρ

 = 1.2 kg/m

3

Δ

P [Pa] = Pressure loss  /  V

ZU

  [m

3

/h] = Supply air volume

NL

 (mm)

Nozzle configuration 600

1200

B

0,95

1,58

C

1,75

2,91

D

2,59

4,32

E

4,44

7,40

V

K Ps

=

The Pa meter is not included in the delivery.

Vzu (m

3

/h)

0 20 40 60 80 100

200

300

0

2

0

4

0

6

0

8

0

100

200

300

'

P (Pa.)

600-B

600-C

600-D

600-E

1200-C

1200-B

1200-D

1200-E

Содержание DISA-360

Страница 1: ...Ferdinand Schad KG Steigstra e 25 27 D 78600 Kolbingen Telephone 49 0 74 63 980 0 Fax 49 0 74 63 980 200 info schako de www schako de Installation Mounting and Maintenance DISA 360...

Страница 2: ...ered model 4 Function 4 Installation and commissioning 5 Operating conditions 5 Material reception 5 Transport lifting and handling 5 Storage 5 Installation 6 Mounting 6 Hydraulic connections 6 Connec...

Страница 3: ...lacement of defec tive materials Recycling The inspection installation hydraulic connection and com missioning of the device must be carried out by qualified skilled personnel only in compliance with...

Страница 4: ...ing or optionally 4 pipe system cooling and heating The registers consist of cop per pipes 12 mm in thickness aluminium ribs and a steel frame Grille 3 Possible designs perforated sheet grille made of...

Страница 5: ...Foldable perforated sheet perforation 6 mm B Nozzle configuration B 592 total width 592 mm 592 total length 592 mm WS1 Water connection left H Connection horizontal AS1 Number of connecting pieces 1 c...

Страница 6: ...void excessive tighten ing or twisting of the register connections Make sure that places that are intended as openings for air admission and air discharge are free of pipes electric ca bles crossbeams...

Страница 7: ...ends on the select ed model Please follow the instructions enclosed with each model Adjustment of the air deflection blades To regulate the air flow ro tate the air deflection blades manually With blo...

Страница 8: ...by spraying it with a non aggressive cleaner Hydraulic connections were tightened properly and exhib it no leaks Connecting and fastening elements have been sufficiently tightened Adequate access for...

Страница 9: ...lean it by spraying it with water or compressed air or by evacua tion Please do not use any scouring agents for cleaning since these materials may impair or damage the DISA 360 gal vanised steel alumi...

Страница 10: ...e nozzles at the primary air plenum box see drawing and the other end is con nected to the hose connection of a Pa meter The values read on the meter and the following formula can be used to to determ...

Страница 11: ...or Install thermostat in a different place Clogging of the cooling heating register Clean the register in accordance with the maintenance instructions The unit is losing water Condensate in the regist...